- CROSS-AUS Newsletter 1 (1)
- CROSS-AUS Newsletter 4 (2)
- CROSS-AUS [sub-heading only] (3)
- CROSS-UK Newsletter 1 (1)
- CROSS-UK Newsletter 6 (1)
- CROSS-UK Newsletter 12 (2)
- CROSS-UK Newsletter 13 (1)
- CROSS-UK Newsletter 19 (1)
- CROSS-UK Newsletter 21 (1)
- CROSS-UK Newsletter 24 (1)
- CROSS-UK Newsletter 30 (1)
- CROSS-UK Newsletter 32 (1)
- CROSS-UK Newsletter 37 (2)
- CROSS-UK Newsletter 39 (1)
- CROSS-UK Newsletter 40 (1)
- CROSS-UK Newsletter 41 (1)
- CROSS-UK Newsletter 45 (1)
- CROSS-UK Newsletter 46 (2)
- CROSS-UK Newsletter 47 (1)
- CROSS-UK Newsletter 48 (1)
- CROSS-UK Newsletter 49 (1)
- CROSS-UK Newsletter 50 (1)
- CROSS-UK Newsletter 51 (1)
- CROSS-UK Newsletter 53 (1)
- CROSS-UK Newsletter 54 (1)
- CROSS-UK Newsletter 55 (1)
- CROSS-UK Newsletter 58 (2)
- CROSS-UK Newsletter 59 (2)
- CROSS-UK Newsletter 60 (1)
- CROSS-UK Newsletter 68 (1)
- CROSS-UK [sub-heading only] (27)
- CROSS-US Newsletter 1 (1)
- CROSS-US Newsletter 2 (3)
- CROSS-US [sub-heading only] (4)
- CROSS Newsletter (20)
- CROSS Safety Report (51)
- News [sub-heading only] (6)
CROSS regions
Incorrectly installed tension control bolts could have led to serious consequences
A reporter finds incorrectly installed system HRC preload bolt assemblies, better known as tension control bolts, during a site inspection of a new highway bridge over a railway. The incorrectly fitted bolts could have had major structural implications, and led to other safety risks, if the installation error had not been spotted.
24 May 2023
CROSS Safety Report
Report ID: 1196
Region: CROSS-UK
Accidental partial demolition of a beam
During a site visit, the permanent works design engineer noticed that hydro-demolition of the end of a floor supporting beam had taken place out of sequence. This introduced a pattern of bending moments and shear forces that were not considered in the original design.
6 April 2023
CROSS Safety Report
Report ID: 855
Region: CROSS-UK
Wrong length blind bolts lead to unsafe bridge structure
Bridge strengthening being carried out using blind bolts left a structure in an unsafe condition with traffic loading on it.
20 February 2023
CROSS Safety Report
Report ID: 1185
Region: CROSS-UK
Masonry panels rock in wind due to missing wall ties
Wall ties designed to connect masonry partitions to adjacent steelwork framing were not installed leaving the masonry walls unrestrained. Walls were seen to be rocking in high winds.
17 February 2023
CROSS Safety Report
Report ID: 931
Region: CROSS-UK
Checking reinforcement before concrete pours
A reporter has learned whilst making inspections to keep quiet and pass on any comments to the site manager who can then relay the information to the subcontractors.
10 February 2023
CROSS Safety Report
Report ID: 978
Region: CROSS-UK
Critical welding of structural steelwork missed
The designer of a steelwork roof frame found a critical fabrication error when inspecting steelwork on site before it was erected.
21 November 2022
CROSS Safety Report
Report ID: 1126
Region: CROSS-UK
Inadequate punching shear reinforcement in flat slabs
This report highlights how remedial works were required in a number of residential buildings after inadequate punching shear reinforcement was identified.
14 October 2020
CROSS Safety Report
Report ID: 950
Region: CROSS-UK
Inadequate design and quality assurance on a mandatory seismic retrofit project
A tenant's structural engineer discovers widespread design and related quality problems on a mandatory seismic retrofit project.
1 September 2020
CROSS Safety Report
Report ID: 986
Region: CROSS-US
Failure of existing long-span wood roof truss following installation of new roof-top HVAC units
Failure of an existing long-span wood roof truss following installation of new roof-top Heating, Ventilating, and Air Conditioning (HVAC) units offers lessons in the special challenges of renovations to existing buildings.
1 September 2020
CROSS Safety Report
Report ID: 949
Region: CROSS-US
Mandatory seismic retrofit construction with quality control problems
Standard seismic retrofit details were used for a building with a non-standard foundation, resulting in inadequate connection of structural shear walls to foundations.
1 September 2020
CROSS Safety Report
Report ID: 888
Region: CROSS-US
Submit a report
Your report will make a difference. It will help to create positive change and improve safety.
Our secure and confidential safety reporting system gives professionals the opportunity to share their experiences to help others.