Pre-stressing ducts
A reporter has come across a situation where during grouting of the ducts in a slab, patches of concrete as big as 0.5m x 1m and 30mm thick fell on to the ground creating a safety hazard.
Inadequate foundation reinforcement
Subcontractors carrying out the ground works for a multi-storey development failed to provide sufficient continuity reinforcement in the ground beams.
Multi storey car park defects
A reporter has been concerned for some time that there potentially could be another failure similar to Pipers Row in Wolverhampton and raises their concerns.
Progressive collapse of mill building
Nearby families were evacuated after part of a four-storey former mill building collapsed adjacent to their homes.
Progressive collapse of an old mill building during a fire
An old mill building that was constructed around 1830 collapsed unexpectedly in a fire.
Submit a report
Your report will make a difference. It will help to create positive change and improve safety.
Our secure and confidential safety reporting system gives professionals the opportunity to share their experiences to help others.
Feedback
No feedback has yet been published for this page.