Safety information search results
Filter your results
Products
Project or lifecycle stage
Codes, standards & regulations
Fire incident response
Method of construction
Structural form
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Project delivery methods
Business practice
Risk management
Public incidents
Theme pages
Content type
- CROSS-AUS Newsletter 3 (1)
- CROSS-AUS [sub-heading only] (1)
- CROSS-UK Newsletter 3 (1)
- CROSS-UK Newsletter 6 (1)
- CROSS-UK Newsletter 8 (1)
- CROSS-UK Newsletter 9 (1)
- CROSS-UK Newsletter 15 (1)
- CROSS-UK Newsletter 16 (1)
- CROSS-UK Newsletter 20 (1)
- CROSS-UK Newsletter 35 (1)
- CROSS-UK Newsletter 38 (2)
- CROSS-UK Newsletter 49 (1)
- CROSS-UK Newsletter 51 (1)
- CROSS-UK Newsletter 52 (1)
- CROSS-UK Newsletter 54 (2)
- CROSS-UK Newsletter 56 (1)
- CROSS-UK Newsletter 57 (1)
- CROSS-UK Newsletter 61 (1)
- CROSS-UK [sub-heading only] (17)
- CROSS-US Newsletter 2 (2)
- CROSS-US [sub-heading only] (2)
- CROSS Newsletter (9)
- CROSS Safety Report (33)
- News [sub-heading only] (4)
CROSS regions
Inadequate brick ties in gable walls
A reporter was called to council houses at four different sites, whose upper triangle of cavity wall brickwork on the gable end had fallen out, due to not being tied into the roof.
1 July 2019
CROSS Safety Report
Report ID: 785
Region: CROSS-UK
Repeating the same design mistakes
A correspondent who investigates engineering failures has shared common errors which engineers keep repeating.
1 October 2019
CROSS Safety Report
Report ID: 858
Region: CROSS-UK
Stability of brick walls
A 230mm cantilevered brick wall approximately 1.6m high failed after backfill material was placed behind it, which was not the design intent.
1 April 2015
CROSS Safety Report
Report ID: 475
Region: CROSS-UK
Cantilevered brickwork - fatal collapse during construction
A blade of 270mm cavity brickwork in a temporary condition fell and killed a bricklayer after sixteen scaffold planks were leant against the wall on the side remote from the bricklayer.
1 April 2015
CROSS Safety Report
Report ID: 476
Region: CROSS-UK
Fatal wall collapse at school due to wall climbing
This report has been provided by the Health and Safety Executive (HSE) and once again highlights the potential dangers of freestanding masonry walls.
1 July 2018
CROSS Safety Report
Report ID: 447
Region: CROSS-UK
Mandatory seismic retrofit construction with quality control problems
Standard seismic retrofit details were used for a building with a non-standard foundation, resulting in inadequate connection of structural shear walls to foundations.
1 September 2020
CROSS Safety Report
Report ID: 888
Region: CROSS-US
Near miss when modifying brickwork
A reporter’s experience of creating a new door opening in an existing brick wall on the first floor of an old building is not always as simple as it would appear.
1 February 2020
CROSS Safety Report
Report ID: 847
Region: CROSS-AUS
Inadequate design and quality assurance on a mandatory seismic retrofit project
A tenant's structural engineer discovers widespread design and related quality problems on a mandatory seismic retrofit project.
1 September 2020
CROSS Safety Report
Report ID: 986
Region: CROSS-US
Incomplete casting of composite brick/concrete parapets
A reporter states that during a parapet raising scheme over a mainline railway, a void up to 300mm deep was identified below existing coping bed level.
1 January 2018
CROSS Safety Report
Report ID: 635
Region: CROSS-UK
Wall collapse during house demolition
A reporter describes how poor demolition practice resulted in a wall falling onto a neighbouring property.
1 April 2017
CROSS Safety Report
Report ID: 608
Region: CROSS-UK