Skip to main content

CROSS Safety Report

Large Panel System (LPS) building structural refurbishment issues

Report ID: 201 Published: 1 July 2011 Region: CROSS-UK

This report is over 2 years old

Please be aware that it might contain information that is no longer up to date. We keep all reports available for historic reference and as learning aids.

Overview

A reporter from a firm of consulting engineers’ comments on his experiences when refurbishing 1960s Large Panel Structure (LPS) buildings around 2000.

Key Learning Outcomes

For all built environment professionals:

  • A structural condition assessment should be carried out by a competent engineer prior to carrying out refurbishment work, particularly for LPS buildings

  • The Institution of Structural Engineers publication ‘Appraisal of existing structures' provides guidance for engineers needing to check and report on the adequacy of an existing structure

  • It is good practice for LPS buildings to have a recorded structural history. Their condition and continued structural integrity should be monitored.

  • There can be many problems with climbing masts during refurbishment (as mentioned in this report) and it is recommended that mast climbers are inspected by a Chartered Engineer as well as an inspector

Full Report

Find out more about the Full Report

The Full Report below has been submitted to CROSS and describes the reporter’s experience. The text has been edited for clarity and to ensure anonymity and confidentiality by removing any identifiable details. If you would like to know more about our secure reporting process or submit a report yourself, please visit the reporting to CROSS-UK page.

 

A reporter from a firm of consulting engineers’ comments on his experiences when refurbishing 1960s Large Panel Structure (LPS) buildings around 2000. In blocks of a particular type, he found that a third of the reinforcement had simply been left out in the slabs on some towers.

The slabs were badly cracked on the soffits, so full scale load tests up to 1.5kN/m² were carried out. It was found that deflections were extremely small, and it was assumed that the slabs were effectively arching.

Carbon fibre reinforcement was however added to the soffit of nearly all the slabs with the recommendation that the strengthening should provide only 30 years extra life and that the buildings should be demolished.

Further concerns with the tower blocks were associated with:

  • An external wall of the reinforced concrete (RC) basement structure had been moved off grid some 600mm at the time of building resulting in inadequate load paths so that new steel columns had to be installed

  • The concrete partition walls are essential for resisting accidental forces. Measures were taken to fix them at the ceiling to prevent horizontal movement.

  • Similarly, basement structures were strengthened to allow loads from these partitions to be transferred to the foundations

  • The lounge slabs cannot take accidental loading without some transverse spanning so steel angles have been added to allow for this

  • The reporter’s firm rejects the idea that the top floors cannot be saved from an accidental explosion. Once a single slab starts to fall, the energy will be too high to ensure that the next floor down will stop it.

  • However, by strapping with angles, ceiling to floor, then in theory the top floor of unreinforced concrete walls will not need to take direct tension, so they can take the accidental bending effects

  • The reporter has had instances where lintels in the basement walls have been cut away to save having to shave a door

  • Owners believe the there was no way a flat could take 17kN/m² in all directions and have done nothing. In practice, just a little strengthening and some dedicated lateral thinking and analysis will suffice.

There were also many problems with climbing masts during refurbishment. Fixings were coming loose in windy conditions and the foundations were, in the reporter’s view, completely inadequate. The Health and Safety Executive (HSE) inspection staff and the contractors’ H&S team had no training on this, and only the reporter’s engineers appeared to appreciate the dangers of the shortcuts that were being used. Scaffolding and mast climbers appear to have very different standards of inspection and safety. It is recommended that mast climbers should be inspected by Chartered Engineers as well as inspectors.

Expert Panel Comments

Find out more about the Expert Panels

Expert Panels comment on the reports we receive. They use their experience to help you understand what can be learned from the reports. If you would like to know more, please visit the CROSS-UK Expert Panels page.

There are no Expert Panel comments on this report. The Expert Panels are only asked to comment on selected reports. These are normally reports where there is an opportunity for them to help you understand what can be learned from the report.

 

Submit a report

Your report will make a difference. It will help to create positive change and improve safety.

Our secure and confidential safety reporting system gives professionals the opportunity to share their experiences to help others.