- CROSS-AUS Newsletter 4 (1)
- CROSS-AUS Newsletter 5 (1)
- CROSS-AUS [sub-heading only] (1)
- CROSS-UK Newsletter 2 (3)
- CROSS-UK Newsletter 5 (1)
- CROSS-UK Newsletter 16 (1)
- CROSS-UK Newsletter 24 (1)
- CROSS-UK Newsletter 26 (1)
- CROSS-UK Newsletter 28 (1)
- CROSS-UK Newsletter 29 (2)
- CROSS-UK Newsletter 41 (1)
- CROSS-UK Newsletter 42 (1)
- CROSS-UK Newsletter 43 (1)
- CROSS-UK Newsletter 45 (1)
- CROSS-UK Newsletter 46 (1)
- CROSS-UK Newsletter 49 (1)
- CROSS-UK Newsletter 52 (1)
- CROSS-UK Newsletter 54 (1)
- CROSS-UK Newsletter 55 (1)
- CROSS-UK Newsletter 56 (1)
- CROSS-UK Newsletter 58 (1)
- CROSS-UK Newsletter 59 (3)
- CROSS-UK Newsletter 60 (1)
- CROSS-UK Newsletter 65 (1)
- CROSS-UK Newsletter 67 (1)
- CROSS-UK [sub-heading only] (24)
- CROSS-US Newsletter 2 (1)
- CROSS-US [sub-heading only] (1)
- CROSS Newsletter (17)
- CROSS Safety Report (37)
- News [sub-heading only] (7)
CROSS regions
Poor quality design leads to failure for a small design and build contract
An example of a small design and build contract where poor design and management led to an inadequate structure being built.
6 June 2022
CROSS Safety Report
Report ID: 1088
Region: CROSS-UK
Stone cladding panel concerns
A reporter is concerned in respect of the risk of failure of stone cladding panels.
9 August 2022
CROSS Safety Report
Report ID: 1069
Region: CROSS-UK
Control of temporary works excavation
Poor, high-water content excavated material, slipped into a 15-20m deep borrow pit. The material had slipped to the bottom of the pit partially burying excavation, crushing and screening equipment. If this slip had occurred during working hours, the impact could have been very serious.
17 November 2022
CROSS Safety Report
Report ID: 1146
Region: CROSS-UK
Concerns over execution class categorisation of steel pedestrian bridge
A reporter is concerned in respect of the steelwork execution class, and quality management arrangements, applied to the construction of a public access pedestrian bridge.
21 November 2022
CROSS Safety Report
Report ID: 1149
Region: CROSS-UK
Concern about rebending starter bars
This report concerns the bending and rebending of starter bars on site during the construction of a multi storey tower. The reporter considered that such a practice could compromise the structure under extreme load conditions.
24 May 2023
CROSS Safety Report
Report ID: 1164
Region: CROSS-UK
The use of cast-in ferrules as structural connections
This report highlights several problems that can arise with structural connections between elements when cast-in ferrules (also known as threaded inserts) are used for the anchorage of reinforcing bars.
30 April 2021
CROSS Safety Report
Report ID: 993
Region: CROSS-AUS
Overloading a portal frame with suspended services
A reporter designing a single storey portal frame used a standard roof service loading of 0.25kN/m2. After the project was completed, a tenant for the unit took over fit out and added a considerable amount of sprinkler pipework into the roof. This created local overloading.
21 August 2023
CROSS Safety Report
Report ID: 1195
Region: CROSS-UK
Poorly applied external insulation on buildings
This report concerns external insulation on buildings being inadequately applied and fixed, with poor control of the workmanship standards, leading to potential safety concerns and damage to the property.
21 August 2023
CROSS Safety Report
Report ID: 1203
Region: CROSS-UK
Steelwork splices do not match design calculations
Remedial works had to be carried out after it was found that steelwork splices on site did not match calculations which were retrospectively provided by a contractor.
29 March 2021
CROSS Safety Report
Report ID: 916
Region: CROSS-UK
Timber truss
The reporter has been dealing with an application where the engineer involved discovered proprietary timber girder trusses with some glued joints that have come loose.
1 February 2007
CROSS Safety Report
Report ID: 62
Region: CROSS-UK
Submit a report
Your report will make a difference. It will help to create positive change and improve safety.
Our secure and confidential safety reporting system gives professionals the opportunity to share their experiences to help others.