Safety information search results
Filter your results
Building or structure type
- Bridges (4)
- Buildings
(36)
- Car parks (2)
- Commercial (3)
- Consequence Class 3 buildings (1)
- Education, science & art buildings (3)
- Health care (1)
- Industrial buildings (1)
- Laboratory buildings (1)
- Nuclear & energy buildings (1)
- Public, religious & civic buildings (2)
- Residential (13)
- Stadiums (2)
- Storage buildings (1)
- Theatres & other entertainment buildings (1)
- Transport buildings (1)
- Railways (1)
- Temporary structures (2)
Project or lifecycle stage
Design
Codes, standards & regulations
Fire incident response
Method of construction
Elements & systems
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Organisations
Project delivery methods
Business practice
Risk management
Theme pages
Locations
Content type
- CROSS-AUS Newsletter 5 (2)
- CROSS-UK Newsletter 2 (4)
- CROSS-UK Newsletter 19 (1)
- CROSS-UK Newsletter 29 (2)
- CROSS-UK Newsletter 30 (1)
- CROSS-UK Newsletter 34 (1)
- CROSS-UK Newsletter 35 (1)
- CROSS-UK Newsletter 36 (1)
- CROSS-UK Newsletter 37 (1)
- CROSS-UK Newsletter 44 (2)
- CROSS-UK Newsletter 46 (2)
- CROSS-UK Newsletter 47 (3)
- CROSS-UK Newsletter 48 (3)
- CROSS-UK Newsletter 49 (1)
- CROSS-UK Newsletter 50 (2)
- CROSS-UK Newsletter 51 (1)
- CROSS-UK Newsletter 54 (1)
- CROSS-UK Newsletter 55 (1)
- CROSS-UK Newsletter 59 (2)
- CROSS-UK Newsletter 60 (4)
- CROSS-UK [sub-heading only] (29)
- CROSS-US Newsletter 3 (3)
- CROSS Newsletter (28)
- CROSS Safety Report (46)
- News [sub-heading only] (10)
CROSS regions
Painted faying surfaces leads to connections with insufficient load capacity
Painted, rather than the required unpainted connection faying surfaces, were identified by the Resident Engineer of a reporter's firm during the erection of a primary frame for a large project. The painted surfaces resulted in the connections not having sufficient load carrying capacity and necessitated remedial works.
20 November 2023
CROSS Safety Report
Report ID: 896
Region: CROSS-UK
Steelwork connection design
A reporter was asked to design connections for a multi-storey building for which the frame had been designed by another engineer. The result was a near collapse situation.
1 March 2006
CROSS Safety Report
Report ID: 25
Region: CROSS-UK
Steel portal frame erection
A reporter describes how a steel portal frame collapsed during its erection.
1 March 2006
CROSS Safety Report
Report ID: 20
Region: CROSS-UK
Structural steel - reinforced concrete interface
A reporter describes how the substructure of a building was constructed out of position to the extent that the steel frame could not be erected to tolerance and could not be connected to the holding down bolts.
1 March 2006
CROSS Safety Report
Report ID: 19
Region: CROSS-UK
Girder collapse
The failure was of a two-storey high trussed girder with a 36m span, designed to carry a composite steel and concrete floor at the lower level and a trussed roof at higher level.
1 March 2006
CROSS Safety Report
Report ID: 30
Region: CROSS-UK
Very slender props
A reporter noticed prop that did not have ties installed while carrying out a site inspection.
1 July 2007
CROSS Safety Report
Report ID: 34
Region: CROSS-UK
Roof collapse of warehouse structure under rainwater ponding
This report highlights the structural risk caused by rainwater ponding on relatively flat roofs.
10 May 2021
CROSS Safety Report
Report ID: 969
Region: CROSS-US
Floor vibration in a gym
Vibration within the floor structure of a second floor gym gives rise to concern of structural resonance and possible fatigue of structural members.
26 August 2022
CROSS Safety Report
Report ID: 1106
Region: CROSS-UK
Design of internal partitions for horizontal loads
This report draws attention to the requirement for internal partitions to be designed for horizontal loads from wind and seismic effects in accordance with Section B of the Australian National Construction Code (NCC).
30 April 2021
CROSS Safety Report
Report ID: 1000
Region: CROSS-AUS
Failures of cold formed steel floor systems during construction
This report describes numerous collapses during construction of cold formed steel floor systems caused by lack of bracing/fastening and overloading of an incomplete structure.
10 May 2021
CROSS Safety Report
Report ID: 997
Region: CROSS-US
Submit a report
Your report will make a difference. It will help to create positive change and improve safety.
Our secure and confidential safety reporting system gives professionals the opportunity to share their experiences to help others.