Safety information search results
Filter your results
Building or structure type
Materials
Products
Project or lifecycle stage
Design
Fire incident response
Project type
- Alteration & conversion project (3)
- Assessment project [sub-heading only] (5)
- Conservation & restoration project (1)
- Construction project [sub-heading only] (30)
- Demolition project (5)
- New build (21)
- Refurbishment (2)
- Remediation project (4)
- Repair project (2)
- Strengthening project (1)
- Structural assessment (8)
Method of construction
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Project delivery methods
Business practice
Locations
Content type
- CROSS-AUS Newsletter 3 (1)
- CROSS-AUS Newsletter 4 (2)
- CROSS-AUS [sub-heading only] (3)
- CROSS-UK Newsletter 2 (1)
- CROSS-UK Newsletter 3 (1)
- CROSS-UK Newsletter 4 (1)
- CROSS-UK Newsletter 6 (1)
- CROSS-UK Newsletter 9 (3)
- CROSS-UK Newsletter 12 (1)
- CROSS-UK Newsletter 18 (1)
- CROSS-UK Newsletter 20 (1)
- CROSS-UK Newsletter 26 (2)
- CROSS-UK Newsletter 28 (1)
- CROSS-UK Newsletter 30 (2)
- CROSS-UK Newsletter 31 (1)
- CROSS-UK Newsletter 35 (1)
- CROSS-UK Newsletter 36 (1)
- CROSS-UK Newsletter 38 (1)
- CROSS-UK Newsletter 39 (1)
- CROSS-UK Newsletter 41 (2)
- CROSS-UK Newsletter 45 (1)
- CROSS-UK Newsletter 54 (2)
- CROSS-UK Newsletter 58 (5)
- CROSS-UK Newsletter 59 (1)
- CROSS-UK Newsletter 60 (2)
- CROSS-UK Newsletter 68 (1)
- CROSS-UK [sub-heading only] (28)
- CROSS Newsletter (16)
- CROSS Safety Report (60)
- News [sub-heading only] (5)
CROSS regions
Pre-stressing ducts
A reporter has come across a situation where during grouting of the ducts in a slab, patches of concrete as big as 0.5m x 1m and 30mm thick fell on to the ground creating a safety hazard.
1 October 2008
CROSS Safety Report
Report ID: 89
Region: CROSS-UK
Plastic spacers in slabs
A reporter has spotted plastic rails about 1.5 m long being used to support the bottom rebar mat of a slab.
1 July 2015
CROSS Safety Report
Report ID: 431
Region: CROSS-UK
Balcony construction defects of residential flats
A reporter's firm have been undertaking structural assessments of cantilevered reinforced concrete walkways, which in the majority of cases have been found to be under strength.
1 April 2014
CROSS Safety Report
Report ID: 435
Region: CROSS-UK
Computer analysis and slab design twisting moments
A reporter has noticed on many occasions when checking reinforced concrete and post-tensioned slab designs that engineers often neglect to consider twisting moments when arriving at slab design moments.
1 October 2014
CROSS Safety Report
Report ID: 441
Region: CROSS-UK
Safety issues with composite metal deck floors
A contractor had a near miss when pouring a concrete slab with permanent formwork.
1 January 2012
CROSS Safety Report
Report ID: 288
Region: CROSS-UK
Falsework collapse during slab pour in SE Asia
There was a partial collapse of falsework on a project in Southeast Asia.
1 July 2013
CROSS Safety Report
Report ID: 337
Region: CROSS-UK
Missing rebar identified prior to concrete slab pour
A reporter describes how they often encounter issues such as missing reinforcement while carrying out pre-pour inspections.
1 January 2013
CROSS Safety Report
Report ID: 310
Region: CROSS-UK
Shear failure during demolition
A reporter raises concerns about how a number of buildings being demolished ‘top-down’ have suffered from partial collapse during the process.
1 January 2016
CROSS Safety Report
Report ID: 523
Region: CROSS-UK
Risks from off-site manufacture and hybrid construction
A reporter was recently investigating a ‘near miss’ involving concrete construction in which pre-cast and in-situ concrete were used in combination.
1 January 2016
CROSS Safety Report
Report ID: 529
Region: CROSS-UK
Failure of precast concrete cover slab to circular shaft
A reporter describes how several precast concrete cover slab units collapsed shortly after being installed.
1 April 2015
CROSS Safety Report
Report ID: 505
Region: CROSS-UK