Safety information search results
Filter your results
Building or structure type
Project or lifecycle stage
Design
Operation or occupation
Fire incident response
Construction period
Method of construction
Structural form
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Project delivery methods
Business practice
Risk management
Public incidents
Theme pages
Locations
Content type
- CROSS-AUS Newsletter 3 (1)
- CROSS-AUS Newsletter 5 (1)
- CROSS-AUS [sub-heading only] (1)
- CROSS-UK Newsletter 2 (3)
- CROSS-UK Newsletter 15 (1)
- CROSS-UK Newsletter 16 (1)
- CROSS-UK Newsletter 33 (1)
- CROSS-UK Newsletter 37 (1)
- CROSS-UK Newsletter 43 (1)
- CROSS-UK Newsletter 47 (2)
- CROSS-UK Newsletter 48 (2)
- CROSS-UK Newsletter 52 (1)
- CROSS-UK Newsletter 54 (2)
- CROSS-UK Newsletter 56 (1)
- CROSS-UK Newsletter 58 (1)
- CROSS-UK Newsletter 60 (2)
- CROSS-UK [sub-heading only] (16)
- CROSS Newsletter (13)
- CROSS Safety Report (30)
- News [sub-heading only] (4)
- Third party article (1)
- Third party content (1)
CROSS regions
Installation of epoxy resin adhesive for reinforcing bar anchors
Potentially dangerous installation of resin-anchored reinforcing bars, where epoxy resin was applied at the top of the hole after bars had been inserted.
7 November 2023
CROSS Safety Report
Report ID: 1225
Region: CROSS-AUS
Steelwork connection design
A reporter was asked to design connections for a multi-storey building for which the frame had been designed by another engineer. The result was a near collapse situation.
1 March 2006
CROSS Safety Report
Report ID: 25
Region: CROSS-UK
Differing reinforcement couplers
On a recent project, because of supply problems, the contractor decided to change from the specified rebar couplers (type ‘A’) to those of another manufacturer (type ‘B’).
1 March 2006
CROSS Safety Report
Report ID: 28
Region: CROSS-UK
Structural steel - reinforced concrete interface
A reporter describes how the substructure of a building was constructed out of position to the extent that the steel frame could not be erected to tolerance and could not be connected to the holding down bolts.
1 March 2006
CROSS Safety Report
Report ID: 19
Region: CROSS-UK
CARES Alert: Unregulated reinforcement continuity systems
CARES is investigating unregulated reinforcement continuity systems entering the construction supply chain.
27 April 2021
Third party content
Publisher: CARES
Precast concrete panel fixing
A 1960s flyover was being demolished and an interesting feature came to light how the precast concrete edge panels were fixed.
30 June 2022
CROSS Safety Report
Report ID: 965
Region: CROSS-UK
Preparation of holes in concrete for chemical anchors
Reinforcement intended to be resin anchored into concrete was not anchored, because the resin did not cure, due to contamination within the holes.
6 June 2022
CROSS Safety Report
Report ID: 1096
Region: CROSS-UK
The use of cast-in ferrules as structural connections
This report highlights several problems that can arise with structural connections between elements when cast-in ferrules (also known as threaded inserts) are used for the anchorage of reinforcing bars.
30 April 2021
CROSS Safety Report
Report ID: 993
Region: CROSS-AUS
Misleading instructions for a structural component
A reporter confirms the difficulty encountered whilst endeavouring to ensure cast-in insulated connectors supporting a parapet wall and balustrade were properly fixed.
26 August 2022
CROSS Safety Report
Report ID: 1127
Region: CROSS-UK
Collapse of tank falsework
This report relates to the collapse of falsework erected to construct an in situ, reinforced concrete, circular water retaining structure.
1 October 2009
CROSS Safety Report
Report ID: 150
Region: CROSS-UK