Safety information search results
Filter your results
Building or structure type
Products
Project or lifecycle stage
Design
Operation or occupation
Codes, standards & regulations
Fire incident response
Construction period
Method of construction
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Project delivery methods
Business practice
Public incidents
Locations
Content type
- CROSS-UK Newsletter 7 (1)
- CROSS-UK Newsletter 22 (1)
- CROSS-UK Newsletter 23 (3)
- CROSS-UK Newsletter 32 (1)
- CROSS-UK Newsletter 36 (1)
- CROSS-UK Newsletter 50 (1)
- CROSS-UK Newsletter 54 (1)
- CROSS-UK Newsletter 56 (1)
- CROSS-UK Newsletter 57 (2)
- CROSS-UK Newsletter 59 (1)
- CROSS-UK Newsletter 61 (1)
- CROSS-UK Newsletter 67 (1)
- CROSS-UK Newsletter 68 (1)
- CROSS-UK [sub-heading only] (13)
- CROSS Newsletter (7)
- CROSS Safety Alert (2)
- CROSS Safety Report (25)
- CROSS Topic Paper (2)
- News [sub-heading only] (4)
CROSS regions
Certification of seismic design software
A reporter is concerned about third party certification of seismic design software and believes that users should carefully consider the assumptions that have been made in any such program.
1 October 2013
CROSS Safety Report
Report ID: 377
Region: CROSS-UK
Application of wind load code BS EN 1991 - wind actions
A reporter's concern is about the application of the wind load code BS EN 1991-1-4: 2005 Eurocode 1: Actions on structures - Part 1-4.
1 October 2014
CROSS Safety Report
Report ID: 403
Region: CROSS-UK
Painted faying surfaces leads to connections with insufficient load capacity
Painted, rather than the required unpainted connection faying surfaces, were identified by the Resident Engineer of a reporter's firm during the erection of a primary frame for a large project. The painted surfaces resulted in the connections not having sufficient load carrying capacity and necessitated remedial works.
20 November 2023
CROSS Safety Report
Report ID: 896
Region: CROSS-UK
The risk of collapse of multi-storey CLT buildings during a fire
A reporter presents concerns about the fire safety of multi-storey buildings comprised of cross-laminated timber (CLT) structures.
29 March 2021
CROSS Safety Report
Report ID: 966
Region: CROSS-UK
'Design' for alterations to a dwelling carried out by an unsuitable person
A reporter was called upon to review a design for the removal of a loadbearing wall during the refurbishment of a residence. A builder was already on site but had stopped work since they considered the engineering design to be unsatisfactory and the structural designer was not responding to their queries. The reporter found that the structural design being followed was far from competent.
21 August 2023
CROSS Safety Report
Report ID: 1236
Region: CROSS-UK
Modern methods of construction and robustness
This report relates to the design of a low rise modular building and the requirement, or otherwise, for positive fixings between the superstructure and the substructure.
24 May 2023
CROSS Safety Report
Report ID: 1179
Region: CROSS-UK
Combination load cases in proprietary software cause concern
A reporter is concerned about a widely used software package that does not, in their opinion, generate load combinations in accordance with the Eurocodes being followed.
18 October 2023
CROSS Safety Report
Report ID: 1170
Region: CROSS-UK
Incompetent design of simple steel beams
This report concerns designs for simple steel beams submitted to building control bodies under Part A of the Building Regulations. The reporter, a checking engineer for a building control body, was not able to accept the effective length and restraints assumed in a number of submitted designs. Most originated from individuals who used proprietary structural design computer packages without, i...
24 May 2023
CROSS Safety Report
Report ID: 1183
Region: CROSS-UK
Wind adjacent to tall buildings
Reports to CROSS have raised concerns about the design of temporary works to resist wind loading in urban environments.
1 December 2015
CROSS Safety Alert
Region: CROSS-UK, CROSS-AUS, CROSS-US
Building regulations submissions
This report has been written on behalf of a group of senior local government structural engineers who refer to previous CROSS newsletters and in particular the reports relating to the poor quality of building regulation submissions and lack of checking resources.
1 July 2007
CROSS Safety Report
Report ID: 65
Region: CROSS-UK
Submit a report
Your report will make a difference. It will help to create positive change and improve safety.
Our secure and confidential safety reporting system gives professionals the opportunity to share their experiences to help others.