Safety information search results
Filter your results
Building or structure type
Materials
Products
Project or lifecycle stage
Design
Fire incident response
Project type
- Alteration & conversion project (3)
- Assessment project [sub-heading only] (5)
- Conservation & restoration project (1)
- Construction project [sub-heading only] (30)
- Demolition project (5)
- New build (21)
- Refurbishment (2)
- Remediation project (4)
- Repair project (2)
- Strengthening project (1)
- Structural assessment (8)
Method of construction
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Project delivery methods
Business practice
Locations
Content type
- CROSS-AUS Newsletter 3 (1)
- CROSS-AUS Newsletter 4 (2)
- CROSS-AUS [sub-heading only] (3)
- CROSS-UK Newsletter 2 (1)
- CROSS-UK Newsletter 3 (1)
- CROSS-UK Newsletter 4 (1)
- CROSS-UK Newsletter 6 (1)
- CROSS-UK Newsletter 9 (3)
- CROSS-UK Newsletter 12 (1)
- CROSS-UK Newsletter 18 (1)
- CROSS-UK Newsletter 20 (1)
- CROSS-UK Newsletter 26 (2)
- CROSS-UK Newsletter 28 (1)
- CROSS-UK Newsletter 30 (2)
- CROSS-UK Newsletter 31 (1)
- CROSS-UK Newsletter 35 (1)
- CROSS-UK Newsletter 36 (1)
- CROSS-UK Newsletter 38 (1)
- CROSS-UK Newsletter 39 (1)
- CROSS-UK Newsletter 41 (2)
- CROSS-UK Newsletter 45 (1)
- CROSS-UK Newsletter 54 (2)
- CROSS-UK Newsletter 58 (5)
- CROSS-UK Newsletter 59 (1)
- CROSS-UK Newsletter 60 (2)
- CROSS-UK Newsletter 68 (1)
- CROSS-UK [sub-heading only] (28)
- CROSS Newsletter (16)
- (-) CROSS Safety Report (60)
- News [sub-heading only] (5)
CROSS regions
Accidental partial demolition of a beam
During a site visit, the permanent works design engineer noticed that hydro-demolition of the end of a floor supporting beam had taken place out of sequence. This introduced a pattern of bending moments and shear forces that were not considered in the original design.
6 April 2023
CROSS Safety Report
Report ID: 855
Region: CROSS-UK
Failure of prestressed hollowcore units during storage and transport
A reporter shares their experience of the failure of prestressed hollowcore units during storage and transport.
1 June 2022
CROSS Safety Report
Report ID: 748
Region: CROSS-UK
Punching shear design spreadsheets
This is a technical note from a reporter about the methods their firm uses for punching shear design because there was concern about punching shear design spreadsheets possibly leading to potentially unsafe situations. .
28 March 2023
CROSS Safety Report
Report ID: 830
Region: CROSS-UK
Understanding finite element analysis for pile caps
A reporter questions the validity of using two-dimensional finite element (2D FE) shells to model structural elements such as pile caps.
18 October 2023
CROSS Safety Report
Report ID: 1152
Region: CROSS-UK
RAAC assessment undertaken by persons not suitably experienced
A reinforced aerated autoclaved concrete (RAAC) assessment was carried out by persons who did not appear to have appropriate experience, potentially putting building users at risk of harm.
21 August 2023
CROSS Safety Report
Report ID: 1224
Region: CROSS-UK
Concern over modelling of concrete frame building for construction stage
Independent check shows inadequate modelling of concrete frame building with transfer slab.
10 March 2022
CROSS Safety Report
Report ID: 1073
Region: CROSS-UK
Continuously threaded reinforcing bar
This report highlights the difficulty of inspecting continuously threaded reinforcing bars to ensure that they have been adequately inserted into the cast-in ferrules.
2 August 2022
CROSS Safety Report
Report ID: 1074
Region: CROSS-AUS
Girder collapse
The failure was of a two-storey high trussed girder with a 36m span, designed to carry a composite steel and concrete floor at the lower level and a trussed roof at higher level.
1 March 2006
CROSS Safety Report
Report ID: 30
Region: CROSS-UK
Design of head track in cold formed steel framing
The reporter noticed that the in-house structural engineer for the steel frame company had not taken account of all the loads in the design of the head track.
1 November 2006
CROSS Safety Report
Report ID: 39
Region: CROSS-UK
Concerns about punching shear in a flat slab
This report concerns potential shear failures in flat slabs. This originates from inconsistent design and detailing of the shear reinforcement where a proprietary shear link system is assumed in the design but not followed in detailing.
13 December 2021
CROSS Safety Report
Report ID: 1050
Region: CROSS-UK
Submit a report
Your report will make a difference. It will help to create positive change and improve safety.
Our secure and confidential safety reporting system gives professionals the opportunity to share their experiences to help others.