Safety information search results
Filter your results
Building or structure type
Project or lifecycle stage
Design
Operation or occupation
Codes, standards & regulations
Fire incident response
Method of construction
Structural form
Elements & systems
Temporary works
Plant & equipment
Utilities
Safety reporting
Project delivery methods
Business practice
Public incidents
Theme pages
Content type
- CROSS-AUS Newsletter 5 (1)
- CROSS-UK Newsletter 1 (1)
- CROSS-UK Newsletter 3 (1)
- CROSS-UK Newsletter 5 (1)
- CROSS-UK Newsletter 6 (1)
- CROSS-UK Newsletter 8 (1)
- CROSS-UK Newsletter 31 (1)
- CROSS-UK Newsletter 37 (1)
- CROSS-UK Newsletter 40 (1)
- CROSS-UK Newsletter 55 (1)
- CROSS-UK Newsletter 61 (1)
- CROSS-UK Newsletter 64 (2)
- CROSS-UK Newsletter 65 (1)
- CROSS-UK Newsletter 67 (1)
- CROSS-UK Newsletter 68 (1)
- CROSS-UK [sub-heading only] (9)
- CROSS Newsletter (7)
- CROSS Safety Alert (1)
- CROSS Safety Report (30)
CROSS regions
Overall stability of building proposed to be provided by metal framing and plasterboard
Metal framing and plasterboard was used to provide lateral stability to a building. The form of construction was later deemed to be unsuitable and extensive remedial works had to be carried out.
24 May 2023
CROSS Safety Report
Report ID: 468
Region: CROSS-UK
Dangerous defects in curtain wall glazing
This report concerns a 5m high vertical glazing system in which the fixings for a panel failed after only four years because of a lack of co-ordination between designers and contractors.
6 April 2023
CROSS Safety Report
Report ID: 762
Region: CROSS-UK
Major safety defects in hospital
A number of construction defects were found in a hospital following the inspection of the external wall system.
29 March 2021
CROSS Safety Report
Report ID: 826
Region: CROSS-UK
Galvanic (bimetallic) corrosion not considered in cladding design
A cladding designer and installer did not consider galvanic (bimetallic) corrosion which led to remedial works being required.
30 June 2022
CROSS Safety Report
Report ID: 811
Region: CROSS-UK
Cladding subcontractor change of connection strategy led to failure
As part of their final design submission, a cladding subcontractor changed the connection strategy for their cladding system. The project structural engineer did not identify the design change and the cladding loading resulted in excessive deflection and some twisting of the primary perimeter steel.
21 August 2023
CROSS Safety Report
Report ID: 1189
Region: CROSS-UK
Poorly applied external insulation on buildings
This report concerns external insulation on buildings being inadequately applied and fixed, with poor control of the workmanship standards, leading to potential safety concerns and damage to the property.
21 August 2023
CROSS Safety Report
Report ID: 1203
Region: CROSS-UK
Cladding fixed to stainless steel
Cladding panels fixed to a stainless steel supporting angle with stainless steel screws failed.
1 November 2005
CROSS Safety Report
Report ID: 7
Region: CROSS-UK
Wind damage to secondary elements
A period of storm force winds, with wind speeds approaching design levels, resulted in damage to secondary roofing and cladding elements.
1 July 2006
CROSS Safety Report
Report ID: 42
Region: CROSS-UK
Facade failure
Large pieces of granite fell without warning from a second floor opening.
1 February 2007
CROSS Safety Report
Report ID: 63
Region: CROSS-UK
Collapse of brickwork cladding
The external leaf of a brickwork pier at first floor level fell down onto the playground of a school adjacent to the main entrance door.
1 October 2007
CROSS Safety Report
Report ID: 84
Region: CROSS-UK
Submit a report
Your report will make a difference. It will help to create positive change and improve safety.
Our secure and confidential safety reporting system gives professionals the opportunity to share their experiences to help others.