Vegetation damage to railway arches
Lack of clarity as to maintenance responsibilities leads to degradation of railway arches.
6 June 2022
CROSS Safety Report
Report ID: 1064
Region: CROSS-UK
Unsafe instructions from a building inspector
On the site for an extension to a domestic property, a building inspector instructed a contractor to excavate a deep trench. The trench was in front of the neighbour's adjacent boundary retaining wall, and left a deep vertical face under the house being extended.
10 March 2022
CROSS Safety Report
Report ID: 1086
Region: CROSS-UK
Potentially unsafe buckling resistance checks using software
A number of anomalies were detected in the outputs from a proprietary structural steelwork design program.
6 June 2022
CROSS Safety Report
Report ID: 1075
Region: CROSS-UK
Preparation of holes in concrete for chemical anchors
Reinforcement intended to be resin anchored into concrete was not anchored, because the resin did not cure, due to contamination within the holes.
6 June 2022
CROSS Safety Report
Report ID: 1096
Region: CROSS-UK
Misleading instructions for a structural component
A reporter confirms the difficulty encountered whilst endeavouring to ensure cast-in insulated connectors supporting a parapet wall and balustrade were properly fixed.
26 August 2022
CROSS Safety Report
Report ID: 1127
Region: CROSS-UK
Control of temporary works excavation
Poor, high-water content excavated material, slipped into a 15-20m deep borrow pit. The material had slipped to the bottom of the pit partially burying excavation, crushing and screening equipment. If this slip had occurred during working hours, the impact could have been very serious.
17 November 2022
CROSS Safety Report
Report ID: 1146
Region: CROSS-UK
Failure of existing basement wall
A basement retaining wall failed when a new basement was formed by excavating 1.8m.
1 July 2014
CROSS Safety Report
Report ID: 385
Region: CROSS-UK
Changes in temporary works scheme
Changes in the construction programme on site led to the construction of the superstructure of a building, without the liner wall below it being completed.
1 April 2017
CROSS Safety Report
Report ID: 603
Region: CROSS-UK
Responsibilities of local authorities for possibly dangerous structures
A reporter, who used to be involved with building control, believes that local authorities have a duty to decide if a danger exists when a member of the public draws their attention to a potentially dangerous situation.
1 January 2014
CROSS Safety Report
Report ID: 348
Region: CROSS-UK
Inadequate of biomass fuel stores
A reporter raises concerns over designs they have come across for biomass storage structures where the appropriate lateral loads have not been considered.
1 July 2015
CROSS Safety Report
Report ID: 512
Region: CROSS-UK
Submit a report
Your report will make a difference. It will help to create positive change and improve safety.