Safety information search results
Filter your results
Building or structure type
Project or lifecycle stage
Design
Operation or occupation
Fire incident response
Method of construction
Structural form
Elements & systems
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Project delivery methods
Business practice
Locations
Content type
- CROSS-AUS Newsletter 1 (1)
- CROSS-AUS [sub-heading only] (1)
- CROSS-UK Newsletter 2 (2)
- CROSS-UK Newsletter 6 (1)
- CROSS-UK Newsletter 12 (1)
- CROSS-UK Newsletter 17 (2)
- CROSS-UK Newsletter 19 (2)
- CROSS-UK Newsletter 21 (1)
- CROSS-UK Newsletter 24 (1)
- CROSS-UK Newsletter 26 (1)
- CROSS-UK Newsletter 28 (1)
- CROSS-UK Newsletter 29 (1)
- CROSS-UK Newsletter 30 (1)
- CROSS-UK Newsletter 34 (1)
- CROSS-UK Newsletter 36 (1)
- CROSS-UK Newsletter 37 (4)
- CROSS-UK Newsletter 40 (1)
- CROSS-UK Newsletter 45 (1)
- CROSS-UK Newsletter 46 (1)
- CROSS-UK Newsletter 47 (1)
- CROSS-UK Newsletter 51 (1)
- CROSS-UK Newsletter 54 (1)
- CROSS-UK Newsletter 55 (1)
- CROSS-UK Newsletter 56 (2)
- CROSS-UK Newsletter 57 (1)
- CROSS-UK Newsletter 58 (3)
- CROSS-UK Newsletter 60 (1)
- CROSS-UK Newsletter 65 (1)
- CROSS-UK [sub-heading only] (32)
- CROSS Newsletter (18)
- CROSS Safety Report (45)
- News [sub-heading only] (8)
CROSS regions
Unauthorised alterations to Light Gauge Steel Framing on site
Concerns were raised after Light Gauge Steel Framing (LGSF) acting as a structural system was trimmed locally on site to accommodate the installation of balcony brackets without approval from the design team.
1 July 2018
CROSS Safety Report
Report ID: 669
Region: CROSS-UK
Poor quality of construction and lack of supervision on a block of flats
Concerns are raised over poor quality construction and a lack of supervision on a residential block of flats.
1 July 2017
CROSS Safety Report
Report ID: 672
Region: CROSS-UK
Dangerous alterations to steel beam supports
A local authority building control officer went to site and witnessed on an upper floor that the columns had been removed out of sequence, before the new frame had been constructed.
1 October 2015
CROSS Safety Report
Report ID: 479
Region: CROSS-UK
Issues with imported steel
Defective steel, says a reporter, was found in a major retail store where the material had been imported from a supplier overseas.
1 October 2014
CROSS Safety Report
Report ID: 474
Region: CROSS-UK
Columns missing due to 3D modelling
A new eight storey residential concrete frame building was being constructed and several columns were omitted from the ground and first floor level drawings, says a reporter.
1 January 2017
CROSS Safety Report
Report ID: 614
Region: CROSS-UK
Changes in temporary works scheme
Changes in the construction programme on site led to the construction of the superstructure of a building, without the liner wall below it being completed.
1 April 2017
CROSS Safety Report
Report ID: 603
Region: CROSS-UK
Unbraced temporary props
An alarming photograph has been sent by a contributor.
1 January 2015
CROSS Safety Report
Report ID: 482
Region: CROSS-UK
Design responsibility for temporary stability of steel frame building
A reporter raises concerns about the division of responsibility for the temporary stability of a four-storey steel frame structure with precast concrete planks and a structural topping.
1 April 2019
CROSS Safety Report
Report ID: 789
Region: CROSS-UK
Missing punching shear reinforcement in concrete slabs
A reporter raises concerns of how two separate engineers observed the omission of design punching shear reinforcement prior to slab pours being undertaken on two different sites.
1 April 2020
CROSS Safety Report
Report ID: 906
Region: CROSS-UK
No structural design for steel portal frame building
A reporter is concerned that, in some cases, no structural design is carried out for steel portal framed buildings.
1 January 2020
CROSS Safety Report
Report ID: 866
Region: CROSS-UK