Safety information search results
Filter your results
Building or structure type
Products
Project or lifecycle stage
Design
Operation or occupation
Codes, standards & regulations
Fire incident response
Construction period
Method of construction
Structural form
Elements & systems
Temporary works
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Project delivery methods
Business practice
Risk management
Public incidents
Theme pages
Locations
Content type
- CROSS-UK Newsletter 38 (1)
- CROSS-UK Newsletter 45 (1)
- CROSS-UK Newsletter 46 (1)
- CROSS-UK Newsletter 47 (2)
- CROSS-UK Newsletter 49 (1)
- CROSS-UK Newsletter 51 (1)
- CROSS-UK Newsletter 59 (1)
- CROSS-UK Newsletter 60 (2)
- CROSS-UK [sub-heading only] (9)
- (-) CROSS Newsletter (10)
- CROSS Safety Report (10)
- News [sub-heading only] (2)
CROSS regions
Cantilevered brickwork - fatal collapse during construction
A blade of 270mm cavity brickwork in a temporary condition fell and killed a bricklayer after sixteen scaffold planks were leant against the wall on the side remote from the bricklayer.
1 April 2015
CROSS Safety Report
Report ID: 476
Region: CROSS-UK
Columns missing due to 3D modelling
A new eight storey residential concrete frame building was being constructed and several columns were omitted from the ground and first floor level drawings, says a reporter.
1 January 2017
CROSS Safety Report
Report ID: 614
Region: CROSS-UK
Widespread fire safety failings in residential blocks
A reporter highlights fire safety issues that were found during investigations of building defects in residential blocks.
1 January 2018
CROSS Safety Report
Report ID: 706
Region: CROSS-UK
Padstones out of position leads to collapse
This report concerns the partial collapse of a terrace of four storey houses during construction due to padstones being placed incorrectly.
1 April 2017
CROSS Safety Report
Report ID: 602
Region: CROSS-UK
Unauthorised alterations to Light Gauge Steel Framing on site
Concerns were raised after Light Gauge Steel Framing (LGSF) acting as a structural system was trimmed locally on site to accommodate the installation of balcony brackets without approval from the design team.
1 July 2018
CROSS Safety Report
Report ID: 669
Region: CROSS-UK
Steel balconies fixed to precast hollowcore floor planks
A reporter is concerned about the suitability of providing a retrofitted steel balcony requiring moment connections to the sides of typical hollowcore floor planks.
1 July 2017
CROSS Safety Report
Report ID: 620
Region: CROSS-UK
Poor quality of construction and lack of supervision on a block of flats
Concerns are raised over poor quality construction and a lack of supervision on a residential block of flats.
1 July 2017
CROSS Safety Report
Report ID: 672
Region: CROSS-UK
Fire protection of mixed hot/cold rolled steel structure
This report describes how a high-rise building had to be remediated after it was found there was insufficient fire protection encasement of structural elements.
1 July 2020
CROSS Safety Report
Report ID: 921
Region: CROSS-UK
Inadequate punching shear reinforcement in flat slabs
This report highlights how remedial works were required in a number of residential buildings after inadequate punching shear reinforcement was identified.
14 October 2020
CROSS Safety Report
Report ID: 950
Region: CROSS-UK
Workmanship in domestic buildings
A reporter has raised concerns after discovering a steel beam on site had its web cut away at the support without approval from the design engineer.
14 October 2020
CROSS Safety Report
Report ID: 971
Region: CROSS-UK
Submit a report
Your report will make a difference. It will help to create positive change and improve safety.