Safety information search results
Filter your results
Building or structure type
Building height
Products
Project or lifecycle stage
Operation or occupation
Codes, standards & regulations
Fire incident response
Construction period
Method of construction
Structural form
Elements & systems
Temporary works
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Project delivery methods
Business practice
Risk management
Public incidents
Theme pages
Locations
CROSS regions
Steelwork splices do not match design calculations
Remedial works had to be carried out after it was found that steelwork splices on site did not match calculations which were retrospectively provided by a contractor.
29 March 2021
CROSS Safety Report
Report ID: 916
Region: CROSS-UK
Asymmetric bridge design and construction – a near miss
During the construction stage of an arch footbridge a design error was identified that had been indirectly revealed by an associated error in construction.
1 October 2011
CROSS Safety Report
Report ID: 262
Region: CROSS-UK
Managing changes to design
In the correspondent's experience, change is the root of many of the problems discussed in the current debate about standards of construction.
1 July 2019
CROSS Safety Report
Report ID: 822
Region: CROSS-AUS
Bridge bearing design and installation - further concerns raised
A reporter says that the issue of successful co-ordination between designers, contractors and specialist bearing suppliers is one they have experienced.
1 January 2019
CROSS Safety Report
Report ID: 796
Region: CROSS-UK
Quality of design and construction of a major bridge structure
This report concerns the design and installation of the bridge bearing zones on a new prestressed precast concrete viaduct.
1 October 2018
CROSS Safety Report
Report ID: 781
Region: CROSS-UK
Steelwork connection design
A reporter is concerned that on small domestic projects, steelwork fabricators are appointed who do not have the expertise to design connections or prepare fabrication drawings.
1 October 2013
CROSS Safety Report
Report ID: 393
Region: CROSS-UK
Columns missing due to 3D modelling
A new eight storey residential concrete frame building was being constructed and several columns were omitted from the ground and first floor level drawings, says a reporter.
1 January 2017
CROSS Safety Report
Report ID: 614
Region: CROSS-UK
Submit a report
Your report will make a difference. It will help to create positive change and improve safety.
Our secure and confidential safety reporting system gives professionals the opportunity to share their experiences to help others.