Safety information search results
Filter your results
Project or lifecycle stage
Design
Operation or occupation
Codes, standards & regulations
Fire incident response
Construction period
Method of construction
Structural form
Temporary works
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Project delivery methods
Business practice
Public incidents
Theme pages
Locations
Content type
- CROSS-UK Newsletter 2 (2)
- CROSS-UK Newsletter 29 (2)
- CROSS-UK Newsletter 46 (1)
- CROSS-UK Newsletter 54 (1)
- CROSS-UK Newsletter 55 (1)
- CROSS-UK Newsletter 59 (2)
- CROSS-UK Newsletter 60 (1)
- CROSS-UK Newsletter 65 (1)
- CROSS-UK [sub-heading only] (9)
- CROSS Newsletter (9)
- CROSS Safety Report (14)
- News [sub-heading only] (4)
CROSS regions
Steelwork splices do not match design calculations
Remedial works had to be carried out after it was found that steelwork splices on site did not match calculations which were retrospectively provided by a contractor.
29 March 2021
CROSS Safety Report
Report ID: 916
Region: CROSS-UK
Litigation on divided responsibilities
Divided design responsibilities, says a reporter, are a common source of litigation.
1 January 2013
CROSS Safety Report
Report ID: 229
Region: CROSS-UK
Concerns over execution class categorisation of steel pedestrian bridge
A reporter is concerned in respect of the steelwork execution class, and quality management arrangements, applied to the construction of a public access pedestrian bridge.
21 November 2022
CROSS Safety Report
Report ID: 1149
Region: CROSS-UK
Overloading a portal frame with suspended services
A reporter designing a single storey portal frame used a standard roof service loading of 0.25kN/m2. After the project was completed, a tenant for the unit took over fit out and added a considerable amount of sprinkler pipework into the roof. This created local overloading.
21 August 2023
CROSS Safety Report
Report ID: 1195
Region: CROSS-UK
Poor quality design leads to failure for a small design and build contract
An example of a small design and build contract where poor design and management led to an inadequate structure being built.
6 June 2022
CROSS Safety Report
Report ID: 1088
Region: CROSS-UK
Girder collapse
The failure was of a two-storey high trussed girder with a 36m span, designed to carry a composite steel and concrete floor at the lower level and a trussed roof at higher level.
1 March 2006
CROSS Safety Report
Report ID: 30
Region: CROSS-UK
Steelwork connection design
A reporter was asked to design connections for a multi-storey building for which the frame had been designed by another engineer. The result was a near collapse situation.
1 March 2006
CROSS Safety Report
Report ID: 25
Region: CROSS-UK
Documentation for imported large diameter steel pins
A reporter raises concerns over the possibility that foreign steel with poor, confusing or misleading documentation, is being used on safety critical structures in the UK.
1 January 2013
CROSS Safety Report
Report ID: 299
Region: CROSS-UK
Inadequate bolted connections supporting stairs
Concerns are raised over the safe design and installation of rolled steel angles (RSA) used to support heavy precast stair and landing units.
1 April 2017
CROSS Safety Report
Report ID: 615
Region: CROSS-UK
Design responsibility for temporary stability of steel frame building
A reporter raises concerns about the division of responsibility for the temporary stability of a four-storey steel frame structure with precast concrete planks and a structural topping.
1 April 2019
CROSS Safety Report
Report ID: 789
Region: CROSS-UK
Submit a report
Your report will make a difference. It will help to create positive change and improve safety.
Our secure and confidential safety reporting system gives professionals the opportunity to share their experiences to help others.