- CROSS-AUS Newsletter 4 (1)
- CROSS-AUS Newsletter 5 (3)
- CROSS-AUS [sub-heading only] (1)
- CROSS-UK Newsletter 4 (1)
- CROSS-UK Newsletter 22 (1)
- CROSS-UK Newsletter 28 (1)
- CROSS-UK Newsletter 30 (1)
- CROSS-UK Newsletter 42 (3)
- CROSS-UK Newsletter 46 (1)
- CROSS-UK Newsletter 56 (1)
- CROSS-UK Newsletter 58 (1)
- CROSS-UK Newsletter 62 (1)
- CROSS-UK Newsletter 67 (1)
- CROSS-UK [sub-heading only] (8)
- CROSS Newsletter (6)
- CROSS Safety Report (19)
- News [sub-heading only] (3)
CROSS regions
Control of temporary works excavation
Poor, high-water content excavated material, slipped into a 15-20m deep borrow pit. The material had slipped to the bottom of the pit partially burying excavation, crushing and screening equipment. If this slip had occurred during working hours, the impact could have been very serious.
17 November 2022
CROSS Safety Report
Report ID: 1146
Region: CROSS-UK
Concerns over execution class categorisation of steel pedestrian bridge
A reporter is concerned in respect of the steelwork execution class, and quality management arrangements, applied to the construction of a public access pedestrian bridge.
21 November 2022
CROSS Safety Report
Report ID: 1149
Region: CROSS-UK
The use of cast-in ferrules as structural connections
This report highlights several problems that can arise with structural connections between elements when cast-in ferrules (also known as threaded inserts) are used for the anchorage of reinforcing bars.
30 April 2021
CROSS Safety Report
Report ID: 993
Region: CROSS-AUS
Unsafe excavation practices
A builder undermined the existing footing of a masonry wall without being aware of the risks.
30 July 2021
CROSS Safety Report
Report ID: 1026
Region: CROSS-UK
Grouting of joints between load-bearing prefabricated concrete members
This report highlights the risk of failure if grouted joints between load-bearing prefabricated concrete members are not designed and installed correctly.
30 April 2021
CROSS Safety Report
Report ID: 961
Region: CROSS-AUS
Failure of large aluminium composite panel
This report highlights the importance of correctly designed fixings and anchoring systems for cladding panels to buildings to minimize the risk of failure.
30 April 2021
CROSS Safety Report
Report ID: 962
Region: CROSS-AUS
Scaffolds and traffic protection
A reporter is concerned about the lack of consideration shown both in British Standards and industry guidance regarding the risk of impact of vehicles with scaffolds and thereby putting at risk those working on a scaffold.
1 November 2006
CROSS Safety Report
Report ID: 53
Region: CROSS-UK
Very slender props
A reporter noticed prop that did not have ties installed while carrying out a site inspection.
1 July 2007
CROSS Safety Report
Report ID: 34
Region: CROSS-UK
Falsework support to a bridge – a near miss
This report follows the near collapse of a birdcage scaffold falsework structure during an 800 cubic metre concrete pour on a motorway bridge.
1 October 2012
CROSS Safety Report
Report ID: 333
Region: CROSS-UK
Lack of experience on steel column erection
A reporter highlights how works progressed on site without a detailed method statement being provided by the contractor even though it had been requested.
1 April 2013
CROSS Safety Report
Report ID: 324
Region: CROSS-UK
Submit a report
Your report will make a difference. It will help to create positive change and improve safety.