Safety information search results
Filter your results
Products
Project or lifecycle stage
Operation or occupation
Codes, standards & regulations
Fire incident response
Construction period
Method of construction
Structural form
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Project delivery methods
Business practice
Risk management
Public incidents
Theme pages
Locations
Content type
- CROSS-UK Newsletter 2 (2)
- CROSS-UK Newsletter 19 (1)
- CROSS-UK Newsletter 36 (1)
- CROSS-UK Newsletter 46 (1)
- CROSS-UK Newsletter 47 (1)
- CROSS-UK Newsletter 48 (2)
- CROSS-UK Newsletter 52 (1)
- CROSS-UK Newsletter 54 (1)
- CROSS-UK Newsletter 55 (1)
- CROSS-UK Newsletter 59 (1)
- CROSS-UK [sub-heading only] (9)
- CROSS-US Newsletter 3 (1)
- CROSS Newsletter (10)
- CROSS Safety Report (15)
- News [sub-heading only] (2)
CROSS regions
Cantilever bridge parapet falsework failure
A reporter has experienced the failure of cantilever parapet falsework twice, for different reasons, using two different products during bridge construction.
20 February 2023
CROSS Safety Report
Report ID: 1159
Region: CROSS-UK
Roof collapse of warehouse structure under rainwater ponding
This report highlights the structural risk caused by rainwater ponding on relatively flat roofs.
10 May 2021
CROSS Safety Report
Report ID: 969
Region: CROSS-US
Structural steel - reinforced concrete interface
A reporter describes how the substructure of a building was constructed out of position to the extent that the steel frame could not be erected to tolerance and could not be connected to the holding down bolts.
1 March 2006
CROSS Safety Report
Report ID: 19
Region: CROSS-UK
Steelwork connection design
A reporter was asked to design connections for a multi-storey building for which the frame had been designed by another engineer. The result was a near collapse situation.
1 March 2006
CROSS Safety Report
Report ID: 25
Region: CROSS-UK
Split responsibilities on temporary bracing of steelwork
A contractor removed temporary bracing on site prior to the structure being in a permanent stable state.
1 July 2010
CROSS Safety Report
Report ID: 204
Region: CROSS-UK
Retaining wall excavation collapse
A 6m deep excavation formed for constructing a retaining wall on a domestic project collapsed due to insufficient propping.
1 July 2019
CROSS Safety Report
Report ID: 800
Region: CROSS-UK
Design responsibility for temporary stability of steel frame building
A reporter raises concerns about the division of responsibility for the temporary stability of a four-storey steel frame structure with precast concrete planks and a structural topping.
1 April 2019
CROSS Safety Report
Report ID: 789
Region: CROSS-UK
Issues with imported steel
Defective steel, says a reporter, was found in a major retail store where the material had been imported from a supplier overseas.
1 October 2014
CROSS Safety Report
Report ID: 474
Region: CROSS-UK
Fire protection of mixed hot/cold rolled steel structure
This report describes how a high-rise building had to be remediated after it was found there was insufficient fire protection encasement of structural elements.
1 July 2020
CROSS Safety Report
Report ID: 921
Region: CROSS-UK
Inadequate bolted connections supporting stairs
Concerns are raised over the safe design and installation of rolled steel angles (RSA) used to support heavy precast stair and landing units.
1 April 2017
CROSS Safety Report
Report ID: 615
Region: CROSS-UK
Submit a report