Safety information search results
Filter your results
Building or structure type
Products
Project or lifecycle stage
Operation or occupation
Codes, standards & regulations
Fire incident response
Construction period
Method of construction
Structural form
Elements & systems
Temporary works
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Organisations
Project delivery methods
Business practice
Risk management
Public incidents
Locations
CROSS regions
Effect of staff change on a design
A reporter illustrates how risk can be generated from staff turnover.
1 October 2012
CROSS Safety Report
Report ID: 277
Region: CROSS-UK
Risks from off-site manufacture and hybrid construction
A reporter was recently investigating a ‘near miss’ involving concrete construction in which pre-cast and in-situ concrete were used in combination.
1 January 2016
CROSS Safety Report
Report ID: 529
Region: CROSS-UK
Computer analysis and slab design twisting moments
A reporter has noticed on many occasions when checking reinforced concrete and post-tensioned slab designs that engineers often neglect to consider twisting moments when arriving at slab design moments.
1 October 2014
CROSS Safety Report
Report ID: 441
Region: CROSS-UK
Columns missing due to 3D modelling
A new eight storey residential concrete frame building was being constructed and several columns were omitted from the ground and first floor level drawings, says a reporter.
1 January 2017
CROSS Safety Report
Report ID: 614
Region: CROSS-UK
Concrete grade confusion in software
A reporter noticed that the design calculation report generated by a proprietary software package called for ‘concrete characteristic strength = 45N/mm2’, but did not confirm whether this refers to the cylinder or cube strength.
1 April 2019
CROSS Safety Report
Report ID: 788
Region: CROSS-UK
Design responsibility for temporary stability of steel frame building
A reporter raises concerns about the division of responsibility for the temporary stability of a four-storey steel frame structure with precast concrete planks and a structural topping.
1 April 2019
CROSS Safety Report
Report ID: 789
Region: CROSS-UK
Emergency motorway lane closure during concrete repairs
This report highlights how confusion during concrete repair works led to an unplanned emergency lane closure of a bridge carrying a motorway.
1 July 2020
CROSS Safety Report
Report ID: 926
Region: CROSS-UK
Submit a report
Your report will make a difference. It will help to create positive change and improve safety.
Our secure and confidential safety reporting system gives professionals the opportunity to share their experiences to help others.