Safety information search results
Filter your results
Building or structure type
Building height
Products
Project or lifecycle stage
Operation or occupation
Codes, standards & regulations
Fire incident response
Construction period
Method of construction
Structural form
Elements & systems
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Project delivery methods
Business practice
Risk management
Locations
CROSS regions
Missing starter bars
During an inspection the reporter observed that all the continuity starter bars projecting from the wall kicker were in fact loose.
1 July 2007
CROSS Safety Report
Report ID: 37
Region: CROSS-UK
Collapse of tank falsework
This report relates to the collapse of falsework erected to construct an in situ, reinforced concrete, circular water retaining structure.
1 October 2009
CROSS Safety Report
Report ID: 150
Region: CROSS-UK
Safety issues with composite metal deck floors
A contractor had a near miss when pouring a concrete slab with permanent formwork.
1 January 2012
CROSS Safety Report
Report ID: 288
Region: CROSS-UK
Foundation base plates for tower cranes
On two different contracts it was observed that the foundation base plates for tower cranes had suffered from low compaction of the concrete on which they rest.
1 October 2011
CROSS Safety Report
Report ID: 257
Region: CROSS-UK
Compatibility at RC column to slab joint - strong column/weak slab
A reporter who was reviewing the structural design of a commercial building raises concerns over the compatibility at column/slab joints when different grades of concrete are used.
1 April 2012
CROSS Safety Report
Report ID: 296
Region: CROSS-UK
Permanent formwork to slabs
Concerns are raised over deflection issues that are not being considered when using permanent formwork.
1 January 2011
CROSS Safety Report
Report ID: 215
Region: CROSS-UK
Unconservative design of flat slab due to software modelling issues
A reporter discusses how a design/modelling problem caused an under-designed reinforced concrete (RC) slab to be constructed.
1 April 2020
CROSS Safety Report
Report ID: 886
Region: CROSS-UK
Checking reinforcement before concrete pours
A reporter shares their concerns about incorrect rebar positioning on site prior to concrete being poured.
1 July 2020
CROSS Safety Report
Report ID: 894
Region: CROSS-UK
Missing punching shear reinforcement in concrete slabs
A reporter raises concerns of how two separate engineers observed the omission of design punching shear reinforcement prior to slab pours being undertaken on two different sites.
1 April 2020
CROSS Safety Report
Report ID: 906
Region: CROSS-UK
Inadequate punching shear reinforcement in flat slabs
This report highlights how remedial works were required in a number of residential buildings after inadequate punching shear reinforcement was identified.
14 October 2020
CROSS Safety Report
Report ID: 950
Region: CROSS-UK
Submit a report
Your report will make a difference. It will help to create positive change and improve safety.
Our secure and confidential safety reporting system gives professionals the opportunity to share their experiences to help others.