Safety information search results
Filter your results
Building or structure type
Project or lifecycle stage
Design
Operation or occupation
Codes, standards & regulations
Fire incident response
Construction period
Method of construction
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Project delivery methods
Business practice
Public incidents
Locations
Content type
- CROSS-AUS Newsletter 1 (1)
- CROSS-AUS Newsletter 2 (2)
- CROSS-AUS Newsletter 4 (3)
- CROSS-AUS Newsletter 5 (2)
- CROSS-AUS [sub-heading only] (6)
- CROSS-UK Newsletter 1 (1)
- CROSS-UK Newsletter 2 (2)
- CROSS-UK Newsletter 4 (3)
- CROSS-UK Newsletter 5 (1)
- CROSS-UK Newsletter 6 (1)
- CROSS-UK Newsletter 12 (1)
- CROSS-UK Newsletter 13 (2)
- CROSS-UK Newsletter 16 (1)
- CROSS-UK Newsletter 17 (2)
- CROSS-UK Newsletter 19 (1)
- CROSS-UK Newsletter 21 (1)
- CROSS-UK Newsletter 22 (1)
- CROSS-UK Newsletter 24 (1)
- CROSS-UK Newsletter 28 (2)
- CROSS-UK Newsletter 30 (1)
- CROSS-UK Newsletter 31 (2)
- CROSS-UK Newsletter 34 (2)
- CROSS-UK Newsletter 35 (2)
- CROSS-UK Newsletter 37 (1)
- CROSS-UK Newsletter 38 (1)
- CROSS-UK Newsletter 39 (1)
- CROSS-UK Newsletter 40 (1)
- CROSS-UK Newsletter 42 (2)
- CROSS-UK Newsletter 43 (2)
- CROSS-UK Newsletter 44 (3)
- CROSS-UK Newsletter 45 (1)
- CROSS-UK Newsletter 46 (2)
- CROSS-UK Newsletter 51 (1)
- CROSS-UK Newsletter 52 (1)
- CROSS-UK Newsletter 53 (1)
- CROSS-UK Newsletter 54 (1)
- CROSS-UK Newsletter 55 (1)
- CROSS-UK Newsletter 56 (1)
- CROSS-UK Newsletter 58 (1)
- CROSS-UK Newsletter 59 (1)
- CROSS-UK Newsletter 62 (1)
- CROSS-UK Newsletter 67 (1)
- CROSS-UK [sub-heading only] (46)
- CROSS-US Newsletter 1 (1)
- CROSS-US [sub-heading only] (1)
- CROSS Newsletter (29)
- CROSS Safety Report (67)
- News [sub-heading only] (9)
CROSS regions
Object rolling into live carriageway
A disc of concrete rolled from a construction area onto a live carriageway, colliding with a passing vehicle.
6 June 2022
Report ID: 1089
Region: CROSS-UK
Control of temporary works excavation
Poor, high-water content excavated material, slipped into a 15-20m deep borrow pit. The material had slipped to the bottom of the pit partially burying excavation, crushing and screening equipment. If this slip had occurred during working hours, the impact could have been very serious.
17 November 2022
CROSS Safety Report
Report ID: 1146
Region: CROSS-UK
Cantilever bridge parapet falsework failure
A reporter has experienced the failure of cantilever parapet falsework twice, for different reasons, using two different products during bridge construction.
20 February 2023
CROSS Safety Report
Report ID: 1159
Region: CROSS-UK
The use of cast-in ferrules as structural connections
This report highlights several problems that can arise with structural connections between elements when cast-in ferrules (also known as threaded inserts) are used for the anchorage of reinforcing bars.
30 April 2021
CROSS Safety Report
Report ID: 993
Region: CROSS-AUS
Unsafe excavation practices
A builder undermined the existing footing of a masonry wall without being aware of the risks.
30 July 2021
CROSS Safety Report
Report ID: 1026
Region: CROSS-UK
Column stability during erection
A reporter highlights the importance of ensuring steel columns are temporarily supported until they are sufficiently tied and supported by the permanent structure.
13 December 2021
CROSS Safety Report
Report ID: 1038
Region: CROSS-UK
Grouting of joints between load-bearing prefabricated concrete members
This report highlights the risk of failure if grouted joints between load-bearing prefabricated concrete members are not designed and installed correctly.
30 April 2021
CROSS Safety Report
Report ID: 961
Region: CROSS-AUS
Unprotected deep excavation
On a construction site by a busy main road a reporter saw a deep excavation with no internal temporary works.
1 November 2005
CROSS Safety Report
Report ID: 16
Region: CROSS-UK
Inadequate underpinning
Works were stopped on site after it was discovered the contractor had completely ignored the specified 5-bay sequence and timing of the underpinning works shown on the design drawings.
1 April 2007
CROSS Safety Report
Report ID: 72
Region: CROSS-UK
Adapted masonry support props
A reporter has come across adapted masonry support props in use and in their view, they must only be used in the case of limited openings where the masonry can arch over.
1 November 2006
CROSS Safety Report
Report ID: 57
Region: CROSS-UK
Submit a report
Your report will make a difference. It will help to create positive change and improve safety.