Safety information search results
Filter your results
Building or structure type
Materials
Project or lifecycle stage
Design
Operation or occupation
Fire incident response
Project type
- Alteration & conversion project (7)
- Assessment project [sub-heading only] (1)
- Construction project [sub-heading only] (50)
- Demolition project (3)
- Excavation (1)
- Extension project (5)
- Groundworks project (1)
- New build (33)
- Refurbishment (3)
- Remediation project (4)
- Strengthening project (2)
- Structural assessment (1)
- Underpinning project (2)
Method of construction
Structural form
Elements & systems
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Project delivery methods
Business practice
Locations
Content type
- CROSS-AUS Newsletter 1 (2)
- CROSS-AUS [sub-heading only] (2)
- CROSS-UK Newsletter 2 (2)
- CROSS-UK Newsletter 4 (1)
- CROSS-UK Newsletter 6 (1)
- CROSS-UK Newsletter 8 (1)
- CROSS-UK Newsletter 12 (1)
- CROSS-UK Newsletter 14 (1)
- CROSS-UK Newsletter 17 (2)
- CROSS-UK Newsletter 19 (2)
- CROSS-UK Newsletter 20 (1)
- CROSS-UK Newsletter 21 (1)
- CROSS-UK Newsletter 24 (1)
- CROSS-UK Newsletter 26 (1)
- CROSS-UK Newsletter 28 (1)
- CROSS-UK Newsletter 29 (2)
- CROSS-UK Newsletter 30 (2)
- CROSS-UK Newsletter 33 (1)
- CROSS-UK Newsletter 34 (1)
- CROSS-UK Newsletter 35 (1)
- CROSS-UK Newsletter 36 (1)
- CROSS-UK Newsletter 37 (5)
- CROSS-UK Newsletter 39 (1)
- CROSS-UK Newsletter 40 (2)
- CROSS-UK Newsletter 44 (2)
- CROSS-UK Newsletter 45 (2)
- CROSS-UK Newsletter 46 (2)
- CROSS-UK Newsletter 47 (1)
- CROSS-UK Newsletter 48 (1)
- CROSS-UK Newsletter 51 (1)
- CROSS-UK Newsletter 54 (1)
- CROSS-UK Newsletter 55 (2)
- CROSS-UK Newsletter 56 (3)
- CROSS-UK Newsletter 57 (1)
- CROSS-UK Newsletter 58 (3)
- CROSS-UK Newsletter 60 (2)
- CROSS-UK Newsletter 65 (1)
- CROSS-UK [sub-heading only] (50)
- CROSS Newsletter (31)
- CROSS Safety Report (69)
- News [sub-heading only] (13)
CROSS regions
Concerns on stability require prompt action
A reporter was concerned about overall building stability during an extension and conversion project.
1 January 2010
CROSS Safety Report
Report ID: 171
Region: CROSS-UK
Permanent formwork to slabs
Concerns are raised over deflection issues that are not being considered when using permanent formwork.
1 January 2011
CROSS Safety Report
Report ID: 215
Region: CROSS-UK
Effect of staff change on a design
A reporter illustrates how risk can be generated from staff turnover.
1 October 2012
CROSS Safety Report
Report ID: 277
Region: CROSS-UK
Structural assessments of multi-storey car parks
The parking industry has in recent years (2012) seen several MSCPs closed due to structural fears, says a reporter, which begs the question how close were they to structural failure before they were taken out of service?
1 April 2012
CROSS Safety Report
Report ID: 224
Region: CROSS-UK
Stability compromised in school hall
A reporter highlights construction issues that occurred during the construction of a new school hall.
1 January 2012
CROSS Safety Report
Report ID: 242
Region: CROSS-UK
Lack of control on site when underpinning
The concern is in relation to the sequencing of construction and the lack of control on site from competent persons during underpinning works.
1 October 2011
CROSS Safety Report
Report ID: 241
Region: CROSS-UK
Litigation on divided responsibilities
Divided design responsibilities, says a reporter, are a common source of litigation.
1 January 2013
CROSS Safety Report
Report ID: 229
Region: CROSS-UK
Need for licensed builders
A reporter feels certain building work should only be carried out by licensed qualified builders.
1 January 2011
CROSS Safety Report
Report ID: 214
Region: CROSS-UK
Design deficiencies in calculations submitted to a Local Authority
A Local Authority Building Control manager has sent a list which gives twenty nine of the more serious design review queries raised by the building control structural checking process over the last five years.
1 October 2010
CROSS Safety Report
Report ID: 210
Region: CROSS-UK
Split responsibilities on temporary bracing of steelwork
A contractor removed temporary bracing on site prior to the structure being in a permanent stable state.
1 July 2010
CROSS Safety Report
Report ID: 204
Region: CROSS-UK