Safety information search results
Filter your results
Building or structure type
Project or lifecycle stage
Design
Operation or occupation
Fire incident response
Method of construction
Structural form
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Project delivery methods
Business practice
Public incidents
Content type
- CROSS-AUS Newsletter 4 (1)
- CROSS-AUS [sub-heading only] (1)
- CROSS-UK Newsletter 2 (2)
- CROSS-UK Newsletter 12 (1)
- CROSS-UK Newsletter 19 (1)
- CROSS-UK Newsletter 21 (1)
- CROSS-UK Newsletter 42 (1)
- CROSS-UK Newsletter 44 (2)
- CROSS-UK Newsletter 46 (1)
- CROSS-UK Newsletter 47 (1)
- CROSS-UK Newsletter 48 (1)
- CROSS-UK Newsletter 51 (1)
- CROSS-UK Newsletter 58 (1)
- CROSS-UK Newsletter 59 (1)
- CROSS-UK Newsletter 62 (1)
- CROSS-UK Newsletter 67 (2)
- CROSS-UK [sub-heading only] (12)
- CROSS-US Newsletter 2 (3)
- CROSS-US [sub-heading only] (2)
- CROSS Newsletter (8)
- CROSS Safety Report (30)
- News [sub-heading only] (5)
CROSS regions
Understanding finite element analysis for pile caps
A reporter questions the validity of using two-dimensional finite element (2D FE) shells to model structural elements such as pile caps.
18 October 2023
CROSS Safety Report
Report ID: 1152
Region: CROSS-UK
Object rolling into live carriageway
A disc of concrete rolled from a construction area onto a live carriageway, colliding with a passing vehicle.
6 June 2022
Report ID: 1089
Region: CROSS-UK
Unsafe instructions from a building inspector
On the site for an extension to a domestic property, a building inspector instructed a contractor to excavate a deep trench. The trench was in front of the neighbour's adjacent boundary retaining wall, and left a deep vertical face under the house being extended.
10 March 2022
CROSS Safety Report
Report ID: 1086
Region: CROSS-UK
Mobile phone masts
The concern of an overseas reporter is that erection, foundation design and construction, and maintenance of mobile phone masts are not carried out adequately.
1 March 2006
CROSS Safety Report
Report ID: 22
Region: CROSS-UK
Structural steel - reinforced concrete interface
A reporter describes how the substructure of a building was constructed out of position to the extent that the steel frame could not be erected to tolerance and could not be connected to the holding down bolts.
1 March 2006
CROSS Safety Report
Report ID: 19
Region: CROSS-UK
Unsafe excavation practices
A builder undermined the existing footing of a masonry wall without being aware of the risks.
30 July 2021
CROSS Safety Report
Report ID: 1026
Region: CROSS-UK
Column stability during erection
A reporter highlights the importance of ensuring steel columns are temporarily supported until they are sufficiently tied and supported by the permanent structure.
13 December 2021
CROSS Safety Report
Report ID: 1038
Region: CROSS-UK
Inadequate design for basement works
An inadequate structural design for alterations to a basement led to structural distress within a substantial five-storey townhouse.
21 November 2022
CROSS Safety Report
Report ID: 1132
Region: CROSS-UK
Defect on site deliberately covered up
A reporter shares an experience they had whilst working for a contractor as an assistant site engineer and provides evidence of the risks associated with the reliance on self-certification of construction.
1 January 2011
CROSS Safety Report
Report ID: 217
Region: CROSS-UK
Piling platform failure
While back screwing an auger, the ground began to fail under the foot of the rig causing it to sink forwards and collapse.
1 January 2012
CROSS Safety Report
Report ID: 271
Region: CROSS-UK
Submit a report
Your report will make a difference. It will help to create positive change and improve safety.
Our secure and confidential safety reporting system gives professionals the opportunity to share their experiences to help others.