Safety information search results
Filter your results
Products
Project or lifecycle stage
Design
Operation or occupation
Codes, standards & regulations
Fire incident response
Construction period
Method of construction
Elements & systems
Temporary works
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Project delivery methods
Business practice
Risk management
Public incidents
Theme pages
Locations
Content type
- CROSS-UK Newsletter 2 (1)
- CROSS-UK Newsletter 9 (1)
- CROSS-UK Newsletter 11 (1)
- CROSS-UK Newsletter 26 (1)
- CROSS-UK Newsletter 31 (2)
- CROSS-UK Newsletter 32 (2)
- CROSS-UK Newsletter 37 (1)
- CROSS-UK Newsletter 45 (1)
- CROSS-UK Newsletter 46 (2)
- CROSS-UK Newsletter 48 (1)
- CROSS-UK Newsletter 52 (2)
- CROSS-UK Newsletter 54 (1)
- CROSS-UK Newsletter 56 (2)
- CROSS-UK Newsletter 59 (2)
- CROSS-UK Newsletter 60 (2)
- CROSS-UK Newsletter 65 (1)
- CROSS-UK Newsletter 67 (1)
- CROSS-UK [sub-heading only] (21)
- CROSS Newsletter (17)
- CROSS Safety Report (27)
- News [sub-heading only] (5)
CROSS regions
Poor quality design leads to failure for a small design and build contract
An example of a small design and build contract where poor design and management led to an inadequate structure being built.
6 June 2022
CROSS Safety Report
Report ID: 1088
Region: CROSS-UK
Girder collapse
The failure was of a two-storey high trussed girder with a 36m span, designed to carry a composite steel and concrete floor at the lower level and a trussed roof at higher level.
1 March 2006
CROSS Safety Report
Report ID: 30
Region: CROSS-UK
Connection fixity considerations for steel frame modelling
This report concerns the modelling of joints when using computer programs. In some cases, engineers are applying rotational releases to joints in models but subsequently designing the connections as rigid. This leaves a fundamental mismatch between analysis and design which may lead to unsafe structural connections argues a reporter.
17 November 2022
CROSS Safety Report
Report ID: 1139
Region: CROSS-UK
Steelwork splices do not match design calculations
Remedial works had to be carried out after it was found that steelwork splices on site did not match calculations which were retrospectively provided by a contractor.
29 March 2021
CROSS Safety Report
Report ID: 916
Region: CROSS-UK
Incorrectly installed tension control bolts could have led to serious consequences
A reporter finds incorrectly installed system HRC preload bolt assemblies, better known as tension control bolts, during a site inspection of a new highway bridge over a railway. The incorrectly fitted bolts could have had major structural implications, and led to other safety risks, if the installation error had not been spotted.
24 May 2023
CROSS Safety Report
Report ID: 1196
Region: CROSS-UK
Incompetent design of simple steel beams
This report concerns designs for simple steel beams submitted to building control bodies under Part A of the Building Regulations. The reporter, a checking engineer for a building control body, was not able to accept the effective length and restraints assumed in a number of submitted designs. Most originated from individuals who used proprietary structural design computer packages without, i...
24 May 2023
CROSS Safety Report
Report ID: 1183
Region: CROSS-UK
Car park staircase collapse at construction joint
The top flight of a staircase to a multi-storey concrete car park collapsed approximately 10 years after construction.
1 July 2008
CROSS Safety Report
Report ID: 106
Region: CROSS-UK
Concrete half joints
Poor reinforcement detailing and installation in a half joint led to the collapse of a series of beams and precast concrete slabs.
1 January 2008
CROSS Safety Report
Report ID: 88
Region: CROSS-UK
Stability of tenants' mezzanine
A reporter is concerned about structures where cold-rolled sections depend upon the chipboard for their lateral torsional restraint, and to act as a horizontal diaphragm.
1 July 2013
CROSS Safety Report
Report ID: 378
Region: CROSS-UK
Contractor varies structural design intention
A reporter was made aware by the building owner of an unauthorised structural alteration that had been made on site.
1 January 2015
CROSS Safety Report
Report ID: 420
Region: CROSS-UK
Submit a report
Your report will make a difference. It will help to create positive change and improve safety.
Our secure and confidential safety reporting system gives professionals the opportunity to share their experiences to help others.