Painted faying surfaces leads to connections with insufficient load capacity
Painted, rather than the required unpainted connection faying surfaces, were identified by the Resident Engineer of a reporter's firm during the erection of a primary frame for a large project. The painted surfaces resulted in the connections not having sufficient load carrying capacity and necessitated remedial works.
20 November 2023
CROSS Safety Report
Report ID: 896
Region: CROSS-UK
Stone cladding panel concerns
A reporter is concerned in respect of the risk of failure of stone cladding panels.
9 August 2022
CROSS Safety Report
Report ID: 1069
Region: CROSS-UK
Preparation of holes in concrete for chemical anchors
Reinforcement intended to be resin anchored into concrete was not anchored, because the resin did not cure, due to contamination within the holes.
6 June 2022
CROSS Safety Report
Report ID: 1096
Region: CROSS-UK
Failure of large aluminium composite panel
This report highlights the importance of correctly designed fixings and anchoring systems for cladding panels to buildings to minimize the risk of failure.
30 April 2021
CROSS Safety Report
Report ID: 962
Region: CROSS-AUS
Masonry panels rock in wind due to missing wall ties
Wall ties designed to connect masonry partitions to adjacent steelwork framing were not installed leaving the masonry walls unrestrained. Walls were seen to be rocking in high winds.
17 February 2023
CROSS Safety Report
Report ID: 931
Region: CROSS-UK
Incorrectly installed tension control bolts could have led to serious consequences
A reporter finds incorrectly installed system HRC preload bolt assemblies, better known as tension control bolts, during a site inspection of a new highway bridge over a railway. The incorrectly fitted bolts could have had major structural implications, and led to other safety risks, if the installation error had not been spotted.
24 May 2023
CROSS Safety Report
Report ID: 1196
Region: CROSS-UK
Wrong length blind bolts lead to unsafe bridge structure
Bridge strengthening being carried out using blind bolts left a structure in an unsafe condition with traffic loading on it.
20 February 2023
CROSS Safety Report
Report ID: 1185
Region: CROSS-UK
Cantilever bridge parapet falsework failure
A reporter has experienced the failure of cantilever parapet falsework twice, for different reasons, using two different products during bridge construction.
20 February 2023
CROSS Safety Report
Report ID: 1159
Region: CROSS-UK
Inadequate design and quality assurance on a mandatory seismic retrofit project
A tenant's structural engineer discovers widespread design and related quality problems on a mandatory seismic retrofit project.
1 September 2020
CROSS Safety Report
Report ID: 986
Region: CROSS-US
Mandatory seismic retrofit construction with quality control problems
Standard seismic retrofit details were used for a building with a non-standard foundation, resulting in inadequate connection of structural shear walls to foundations.
1 September 2020
CROSS Safety Report
Report ID: 888
Region: CROSS-US
Submit a report
Your report will make a difference. It will help to create positive change and improve safety.