Safety information search results
Filter your results
Building or structure type
Products
Project or lifecycle stage
Operation or occupation
Codes, standards & regulations
Fire incident response
Construction period
Method of construction
Structural form
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Project delivery methods
Business practice
Public incidents
Locations
Content type
- CROSS-UK Newsletter 2 (2)
- CROSS-UK Newsletter 3 (1)
- CROSS-UK Newsletter 5 (1)
- CROSS-UK Newsletter 6 (1)
- CROSS-UK Newsletter 9 (1)
- CROSS-UK Newsletter 12 (1)
- CROSS-UK Newsletter 13 (2)
- CROSS-UK Newsletter 17 (2)
- CROSS-UK Newsletter 19 (2)
- CROSS-UK Newsletter 21 (1)
- CROSS-UK Newsletter 24 (1)
- CROSS-UK Newsletter 30 (2)
- CROSS-UK Newsletter 31 (2)
- CROSS-UK Newsletter 32 (1)
- CROSS-UK Newsletter 34 (2)
- CROSS-UK Newsletter 35 (1)
- CROSS-UK Newsletter 37 (1)
- CROSS-UK Newsletter 38 (1)
- CROSS-UK Newsletter 40 (1)
- CROSS-UK Newsletter 43 (1)
- CROSS-UK Newsletter 46 (1)
- CROSS-UK Newsletter 54 (1)
- CROSS-UK Newsletter 55 (1)
- CROSS-UK Newsletter 58 (1)
- CROSS-UK Newsletter 59 (1)
- CROSS-UK Newsletter 62 (2)
- CROSS-UK Newsletter 67 (1)
- CROSS-UK [sub-heading only] (30)
- CROSS Newsletter (17)
- CROSS Safety Alert (1)
- CROSS Safety Report (44)
- CROSS Topic Paper (1)
- News [sub-heading only] (6)
- Safety information from CROSS [sub-heading only] (1)
CROSS regions
Control of temporary works excavation
Poor, high-water content excavated material, slipped into a 15-20m deep borrow pit. The material had slipped to the bottom of the pit partially burying excavation, crushing and screening equipment. If this slip had occurred during working hours, the impact could have been very serious.
17 November 2022
CROSS Safety Report
Report ID: 1146
Region: CROSS-UK
Structural stability/integrity of steel frame buildings
There are occasional collapses of steel frame structures during construction and this Alert is to draw attention to matters which need to be borne in mind by designers, fabricators, and contractors.
1 February 2017
CROSS Safety Alert
Region: CROSS-UK, CROSS-AUS, CROSS-US
Accidental partial demolition of a beam
During a site visit, the permanent works design engineer noticed that hydro-demolition of the end of a floor supporting beam had taken place out of sequence. This introduced a pattern of bending moments and shear forces that were not considered in the original design.
6 April 2023
CROSS Safety Report
Report ID: 855
Region: CROSS-UK
Inadequate temporary works on domestic project
An example of inadequate temporary works on a project, and problems reporting the safety issue to the authorities.
14 December 2021
CROSS Safety Report
Report ID: 1044
Region: CROSS-UK
Unsafe working platform
A reporter came across an access platform supported next to an excavated foundation with unstable sides while carrying out an inspection on site.
10 March 2022
CROSS Safety Report
Report ID: 1019
Region: CROSS-UK
Unsafe excavation practices
A builder undermined the existing footing of a masonry wall without being aware of the risks.
30 July 2021
CROSS Safety Report
Report ID: 1026
Region: CROSS-UK
Column stability during erection
A reporter highlights the importance of ensuring steel columns are temporarily supported until they are sufficiently tied and supported by the permanent structure.
13 December 2021
CROSS Safety Report
Report ID: 1038
Region: CROSS-UK
Fire compartmentation detailing issues
Two reports have been received concerning fire compartmentation detailing issues; one on the incorrect installation of fire batts and the other on the incorrect use of intumescent material.
18 August 2021
CROSS Safety Report
Report ID: 1039
Region: CROSS-UK
Removal of internal structure
The roof trusses, 6m above the ground floor, had been left supported on props made by nailing floor joists together; one at each party wall position.
1 July 2006
CROSS Safety Report
Report ID: 46
Region: CROSS-UK
Inadequate underpinning
Works were stopped on site after it was discovered the contractor had completely ignored the specified 5-bay sequence and timing of the underpinning works shown on the design drawings.
1 April 2007
CROSS Safety Report
Report ID: 72
Region: CROSS-UK
Submit a report
Your report will make a difference. It will help to create positive change and improve safety.
Our secure and confidential safety reporting system gives professionals the opportunity to share their experiences to help others.