Safety information search results
Filter your results
Building or structure type
Project or lifecycle stage
Design
Fire incident response
Project type
- Alteration & conversion project (5)
- Conservation & restoration project (1)
- (-) Construction project [sub-heading only] (31)
- Demolition project (1)
- Excavation (1)
- Extension project (2)
- Groundworks project (1)
- New build (11)
- Refurbishment (2)
- Remediation project (4)
- Repair project (1)
- Structural assessment (1)
Construction period
Method of construction
Structural form
Elements & systems
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Project delivery methods
Business practice
Locations
Content type
- CROSS-UK Newsletter 5 (1)
- CROSS-UK Newsletter 7 (1)
- CROSS-UK Newsletter 13 (1)
- CROSS-UK Newsletter 17 (1)
- CROSS-UK Newsletter 20 (1)
- CROSS-UK Newsletter 28 (1)
- CROSS-UK Newsletter 42 (2)
- CROSS-UK Newsletter 44 (2)
- CROSS-UK Newsletter 45 (1)
- CROSS-UK Newsletter 49 (2)
- CROSS-UK Newsletter 50 (1)
- CROSS-UK Newsletter 54 (2)
- CROSS-UK Newsletter 57 (1)
- CROSS-UK Newsletter 58 (2)
- CROSS-UK Newsletter 59 (2)
- CROSS-UK Newsletter 60 (1)
- CROSS-UK Newsletter 65 (1)
- CROSS-UK Newsletter 67 (1)
- CROSS-UK [sub-heading only] (20)
- CROSS Newsletter (14)
- CROSS Safety Report (31)
- News [sub-heading only] (4)
CROSS regions
Lighting pole strikes live overhead cable
An excavator operator accidentally struck a live overhead cable during the installation of a lighting pole.
1 April 2017
CROSS Safety Report
Report ID: 605
Region: CROSS-UK
Building extension causes snow drifting failure
The reporter feels that structural engineers are failing to realise the implications of creating a valley or an upstand and the potential for snow drift to occur.
1 April 2018
CROSS Safety Report
Report ID: 736
Region: CROSS-UK
Inadequate structural design on industrial steel structures
A reporter's firm believes that steel structures associated with plant are being erected without a design being carried out by a structural engineer and are therefore potentially dangerous.
1 April 2019
CROSS Safety Report
Report ID: 804
Region: CROSS-UK
Design responsibility for temporary stability of steel frame building
A reporter raises concerns about the division of responsibility for the temporary stability of a four-storey steel frame structure with precast concrete planks and a structural topping.
1 April 2019
CROSS Safety Report
Report ID: 789
Region: CROSS-UK
Unauthorised structural alterations to accommodate drainpipes
A reporter became aware of cases where main structural steel sections were ‘butchered’ on site to accommodate drainpipes.
1 July 2020
CROSS Safety Report
Report ID: 902
Region: CROSS-UK
Structural issues with cladding
A reporter who investigates cladding failures shares common issues they have encountered.
1 April 2020
CROSS Safety Report
Report ID: 904
Region: CROSS-UK
Fire risks in multi-storey car parks
A reporter is concerned by the reluctance of the industry to voluntarily take on board and proactively react to the lessons learnt from the fire at the Echo Arena car park in Liverpool.
14 October 2020
CROSS Safety Report
Report ID: 940
Region: CROSS-UK
No structural design for steel portal frame building
A reporter is concerned that, in some cases, no structural design is carried out for steel portal framed buildings.
1 January 2020
CROSS Safety Report
Report ID: 866
Region: CROSS-UK
Products installed without CE-marking due to lower cost
Another report from Germany concerns products that have been delivered and installed on a construction site without any CE marking and Declaration of Performance (DoP) at all.
1 January 2020
CROSS Safety Report
Report ID: 836
Region: CROSS-UK
Post-tensioned slab failure during tendon stressing operations
A reporter disseminates the lessons learned after the end of a slab burst while stressing the tendons in a post-tensioned concrete slab.
1 April 2020
CROSS Safety Report
Report ID: 882
Region: CROSS-UK