Safety information search results
Filter your results
Project or lifecycle stage
Design
Operation or occupation
Fire incident response
Method of construction
Structural form
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Organisations
Project delivery methods
Business practice
Risk management
Public incidents
Theme pages
Content type
- CROSS-AUS Newsletter 5 (2)
- CROSS-UK Newsletter 2 (2)
- CROSS-UK Newsletter 5 (1)
- CROSS-UK Newsletter 16 (1)
- CROSS-UK Newsletter 17 (1)
- CROSS-UK Newsletter 21 (1)
- CROSS-UK Newsletter 29 (2)
- CROSS-UK Newsletter 30 (1)
- CROSS-UK Newsletter 47 (1)
- CROSS-UK Newsletter 48 (2)
- CROSS-UK Newsletter 68 (1)
- CROSS-UK [sub-heading only] (11)
- CROSS-US Newsletter 2 (2)
- CROSS-US [sub-heading only] (2)
- CROSS Newsletter (6)
- CROSS Safety Report (23)
- News [sub-heading only] (2)
CROSS regions
Stone cladding panel concerns
A reporter is concerned in respect of the risk of failure of stone cladding panels.
9 August 2022
CROSS Safety Report
Report ID: 1069
Region: CROSS-UK
Cladding failure in strong winds
A reporter writes with concerns about a repeat failure of building cladding, in severe but not exceptional winds, that saw panels fall to the public street below.
17 February 2023
CROSS Safety Report
Report ID: 1172
Region: CROSS-UK
Incorrectly fixed sheets blow off parapet
This report concerns aluminium coping sheets that blew off the parapet of a block of flats under construction. The reporter says a fierce wind blew off several sheets which fell to the ground about 9m below. A building and a car were damaged but thankfully no one was hurt, although the potential for personal injury or death was significant.
25 May 2023
CROSS Safety Report
Report ID: 1180
Region: CROSS-UK
The use of cast-in ferrules as structural connections
This report highlights several problems that can arise with structural connections between elements when cast-in ferrules (also known as threaded inserts) are used for the anchorage of reinforcing bars.
30 April 2021
CROSS Safety Report
Report ID: 993
Region: CROSS-AUS
Steelwork splices do not match design calculations
Remedial works had to be carried out after it was found that steelwork splices on site did not match calculations which were retrospectively provided by a contractor.
29 March 2021
CROSS Safety Report
Report ID: 916
Region: CROSS-UK
Failure of large aluminium composite panel
This report highlights the importance of correctly designed fixings and anchoring systems for cladding panels to buildings to minimize the risk of failure.
30 April 2021
CROSS Safety Report
Report ID: 962
Region: CROSS-AUS
Structural steel - reinforced concrete interface
A reporter describes how the substructure of a building was constructed out of position to the extent that the steel frame could not be erected to tolerance and could not be connected to the holding down bolts.
1 March 2006
CROSS Safety Report
Report ID: 19
Region: CROSS-UK
Timber truss
The reporter has been dealing with an application where the engineer involved discovered proprietary timber girder trusses with some glued joints that have come loose.
1 February 2007
CROSS Safety Report
Report ID: 62
Region: CROSS-UK
Mobile phone masts
The concern of an overseas reporter is that erection, foundation design and construction, and maintenance of mobile phone masts are not carried out adequately.
1 March 2006
CROSS Safety Report
Report ID: 22
Region: CROSS-UK
Collapse of tank falsework
This report relates to the collapse of falsework erected to construct an in situ, reinforced concrete, circular water retaining structure.
1 October 2009
CROSS Safety Report
Report ID: 150
Region: CROSS-UK
Submit a report
Your report will make a difference. It will help to create positive change and improve safety.
Our secure and confidential safety reporting system gives professionals the opportunity to share their experiences to help others.