Safety information search results
Filter your results
Building or structure type
Materials
Project or lifecycle stage
Design
Operation or occupation
Codes, standards & regulations
Fire incident response
Method of construction
Elements & systems
- Balconies (3)
- Balustrades (2)
- Basements (4)
- Beams (19)
- Bracing (3)
- Cladding (5)
- Columns (10)
- Fasteners & connections (23)
- Foundations (15)
- Light gauge steel framing (1)
- Lintels (2)
- Padstones (3)
- Parapets (1)
- Roofs (5)
- Shear walls (2)
- Slabs (4)
- Trusses (2)
- Wall head restraints (2)
- Walls (21)
- Wall ties (2)
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Project delivery methods
Business practice
Public incidents
Content type
- CROSS-AUS Newsletter 2 (1)
- CROSS-AUS Newsletter 4 (2)
- CROSS-AUS Newsletter 5 (2)
- CROSS-AUS [sub-heading only] (3)
- CROSS-UK Newsletter 2 (3)
- CROSS-UK Newsletter 4 (1)
- CROSS-UK Newsletter 5 (2)
- CROSS-UK Newsletter 6 (1)
- CROSS-UK Newsletter 9 (2)
- CROSS-UK Newsletter 10 (1)
- CROSS-UK Newsletter 12 (2)
- CROSS-UK Newsletter 13 (2)
- CROSS-UK Newsletter 14 (1)
- CROSS-UK Newsletter 16 (1)
- CROSS-UK Newsletter 17 (2)
- CROSS-UK Newsletter 18 (1)
- CROSS-UK Newsletter 19 (1)
- CROSS-UK Newsletter 21 (3)
- CROSS-UK Newsletter 22 (1)
- CROSS-UK Newsletter 24 (1)
- CROSS-UK Newsletter 28 (3)
- CROSS-UK Newsletter 29 (2)
- CROSS-UK Newsletter 30 (3)
- CROSS-UK Newsletter 34 (1)
- CROSS-UK Newsletter 35 (2)
- CROSS-UK Newsletter 36 (1)
- CROSS-UK Newsletter 37 (1)
- CROSS-UK Newsletter 38 (1)
- CROSS-UK Newsletter 41 (1)
- CROSS-UK Newsletter 43 (2)
- CROSS-UK Newsletter 44 (3)
- CROSS-UK Newsletter 46 (3)
- CROSS-UK Newsletter 47 (4)
- CROSS-UK Newsletter 48 (2)
- CROSS-UK Newsletter 49 (2)
- CROSS-UK Newsletter 50 (1)
- CROSS-UK Newsletter 51 (1)
- CROSS-UK Newsletter 52 (1)
- CROSS-UK Newsletter 58 (1)
- CROSS-UK Newsletter 59 (3)
- CROSS-UK Newsletter 62 (1)
- CROSS-UK Newsletter 68 (1)
- CROSS-UK [sub-heading only] (60)
- CROSS-US Newsletter 2 (3)
- CROSS-US [sub-heading only] (3)
- CROSS Newsletter (37)
- CROSS Safety Report (90)
- News [sub-heading only] (8)
CROSS regions
Structural steel - reinforced concrete interface
A reporter describes how the substructure of a building was constructed out of position to the extent that the steel frame could not be erected to tolerance and could not be connected to the holding down bolts.
1 March 2006
CROSS Safety Report
Report ID: 19
Region: CROSS-UK
Inadequate underpinning
Works were stopped on site after it was discovered the contractor had completely ignored the specified 5-bay sequence and timing of the underpinning works shown on the design drawings.
1 April 2007
CROSS Safety Report
Report ID: 72
Region: CROSS-UK
Timber truss
The reporter has been dealing with an application where the engineer involved discovered proprietary timber girder trusses with some glued joints that have come loose.
1 February 2007
CROSS Safety Report
Report ID: 62
Region: CROSS-UK
Unstable building due to modification work
A SCOTCROSS report relates to an old four storey building undergoing modifications.
1 February 2007
CROSS Safety Report
Report ID: 69
Region: CROSS-UK
Steel portal frame erection
A reporter describes how a steel portal frame collapsed during its erection.
1 March 2006
CROSS Safety Report
Report ID: 20
Region: CROSS-UK
Mobile phone masts
The concern of an overseas reporter is that erection, foundation design and construction, and maintenance of mobile phone masts are not carried out adequately.
1 March 2006
CROSS Safety Report
Report ID: 22
Region: CROSS-UK
Scaffolds and traffic protection
A reporter is concerned about the lack of consideration shown both in British Standards and industry guidance regarding the risk of impact of vehicles with scaffolds and thereby putting at risk those working on a scaffold.
1 November 2006
CROSS Safety Report
Report ID: 53
Region: CROSS-UK
Very slender props
A reporter noticed prop that did not have ties installed while carrying out a site inspection.
1 July 2007
CROSS Safety Report
Report ID: 34
Region: CROSS-UK
Demolition risks
This report is about the collapse of a flat slab building that occurred overseas whilst the top floor of the building was being demolished onto the next floor down.
1 January 2008
CROSS Safety Report
Report ID: 96
Region: CROSS-UK
Collapse of a wall during construction
An internal corridor wall collapsed in a school under construction.
1 April 2008
CROSS Safety Report
Report ID: 99
Region: CROSS-UK