Poor quality design leads to failure for a small design and build contract
An example of a small design and build contract where poor design and management led to an inadequate structure being built.
6 June 2022
CROSS Safety Report
Report ID: 1088
Region: CROSS-UK
Fatal wall collapse at school due to wall climbing
This report has been provided by the Health and Safety Executive (HSE) and once again highlights the potential dangers of freestanding masonry walls.
1 July 2018
CROSS Safety Report
Report ID: 447
Region: CROSS-UK
Concerns with propping design to large excavations
Concerns are raised about the design of propping to large excavations and particularly about the design of the connections for a raking prop to a horizontal waler.
1 January 2019
CROSS Safety Report
Report ID: 298
Region: CROSS-UK
Failure of precast concrete 'L' shaped retaining wall
A recent incident occurred on a site, where a temporary precast retaining wall failed leading to a pile of clay approximately 3m high spilling through the wall.
1 July 2014
CROSS Safety Report
Report ID: 433
Region: CROSS-UK
Stability of brick walls
A 230mm cantilevered brick wall approximately 1.6m high failed after backfill material was placed behind it, which was not the design intent.
1 April 2015
CROSS Safety Report
Report ID: 475
Region: CROSS-UK
Cantilevered brickwork - fatal collapse during construction
A blade of 270mm cavity brickwork in a temporary condition fell and killed a bricklayer after sixteen scaffold planks were leant against the wall on the side remote from the bricklayer.
1 April 2015
CROSS Safety Report
Report ID: 476
Region: CROSS-UK
Inadequate end bearings for transfer beams
Whilst advising a steel fabricator on tendering for a transfer structure steel frame, a reporter's firm noticed a serious design error with the bearing pressures at the supports of a transfer beam.
1 October 2017
CROSS Safety Report
Report ID: 644
Region: CROSS-UK
Wind loads acting on timber frame walls for designs to BS 5268-6
A reporter says that the masonry shielding factors in BS 5268-6 (K100 and K200) were substantially reduced when PD 6693-1 for designs to EC5 was produced.
1 April 2019
CROSS Safety Report
Report ID: 624
Region: CROSS-UK
Submit a report
Your report will make a difference. It will help to create positive change and improve safety.
Our secure and confidential safety reporting system gives professionals the opportunity to share their experiences to help others.