Safety information search results
Filter your results
Building or structure type
Project or lifecycle stage
Design
Operation or occupation
Codes, standards & regulations
Fire incident response
Construction period
Method of construction
Structural form
Elements & systems
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Project delivery methods
Business practice
Locations
Content type
- CROSS-UK Newsletter 2 (1)
- CROSS-UK Newsletter 28 (2)
- CROSS-UK Newsletter 29 (2)
- CROSS-UK Newsletter 30 (1)
- CROSS-UK Newsletter 31 (1)
- CROSS-UK Newsletter 34 (3)
- CROSS-UK Newsletter 36 (1)
- CROSS-UK Newsletter 37 (2)
- CROSS-UK Newsletter 38 (2)
- CROSS-UK Newsletter 40 (1)
- CROSS-UK Newsletter 42 (1)
- CROSS-UK Newsletter 44 (3)
- CROSS-UK Newsletter 45 (1)
- CROSS-UK Newsletter 46 (5)
- CROSS-UK Newsletter 47 (7)
- CROSS-UK Newsletter 48 (3)
- CROSS-UK Newsletter 49 (2)
- CROSS-UK Newsletter 50 (3)
- CROSS-UK Newsletter 51 (2)
- CROSS-UK Newsletter 52 (2)
- CROSS-UK Newsletter 54 (3)
- CROSS-UK Newsletter 59 (4)
- CROSS-UK Newsletter 60 (5)
- CROSS-UK Newsletter 61 (1)
- CROSS-UK [sub-heading only] (51)
- (-) CROSS Newsletter (58)
- CROSS Safety Report (58)
- News [sub-heading only] (9)
CROSS regions
Columns missing due to 3D modelling
A new eight storey residential concrete frame building was being constructed and several columns were omitted from the ground and first floor level drawings, says a reporter.
1 January 2017
CROSS Safety Report
Report ID: 614
Region: CROSS-UK
Partial failure of precast concrete tank unit on installation
Concerns are raised after the foot of a precast concrete unit failed during installation, making the unit unstable.
1 April 2017
CROSS Safety Report
Report ID: 626
Region: CROSS-UK
Spalled concrete falls from rear face of drilled hole 26 floors up
A reporter describes how during drilling, an operator over drilled the hole causing spalling on the back face of the concrete.
1 July 2017
CROSS Safety Report
Report ID: 639
Region: CROSS-UK
Unauthorised alterations to Light Gauge Steel Framing on site
Concerns were raised after Light Gauge Steel Framing (LGSF) acting as a structural system was trimmed locally on site to accommodate the installation of balcony brackets without approval from the design team.
1 July 2018
CROSS Safety Report
Report ID: 669
Region: CROSS-UK
Poor quality of construction and lack of supervision on a block of flats
Concerns are raised over poor quality construction and a lack of supervision on a residential block of flats.
1 July 2017
CROSS Safety Report
Report ID: 672
Region: CROSS-UK
Contractor installs incorrect steel grade
A reporter came across an issue where the fabricator had used cold formed S235 commodity steel SHS rather than the specified hot formed S275 structural steel SHS.
1 April 2018
CROSS Safety Report
Report ID: 634
Region: CROSS-UK
Multi-storey car park foundations
Concerns are raised about the integrity of a completed car park structure following poor quality control procedures during construction.
1 October 2017
CROSS Safety Report
Report ID: 630
Region: CROSS-UK
Inadequate end bearings for transfer beams
Whilst advising a steel fabricator on tendering for a transfer structure steel frame, a reporter's firm noticed a serious design error with the bearing pressures at the supports of a transfer beam.
1 October 2017
CROSS Safety Report
Report ID: 644
Region: CROSS-UK
Unconnected steel beam connection
A reporter describes how they came across a completely inadequate steel connection while attending site for another matter.
1 October 2017
CROSS Safety Report
Report ID: 646
Region: CROSS-UK
Failure of fabricated access staging board
A member of a team working on a major bridge reported a close call after the supporting mesh flooring on a new access staging system gave way under his foot.
1 July 2017
CROSS Safety Report
Report ID: 651
Region: CROSS-UK