Safety information search results
Filter your results
Building or structure type
Project or lifecycle stage
Design
Fire incident response
Method of construction
Elements & systems
- Balconies (4)
- Balustrades (9)
- Beams (20)
- Bracing (4)
- Cables (2)
- Canopies (1)
- Ceilings (1)
- Cladding (8)
- Columns (9)
- (-) Fasteners & connections (87)
- Foundations (6)
- Insulation (2)
- Light gauge steel framing (4)
- Padstones (1)
- Parapets (3)
- PV panels (1)
- Roofs (4)
- Slabs (1)
- Tendons (1)
- Trusses (3)
- Walls (5)
- Wall ties (1)
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Project delivery methods
Business practice
Public incidents
Theme pages
Content type
- CROSS-AUS Newsletter 1 (1)
- CROSS-AUS Newsletter 3 (2)
- CROSS-AUS Newsletter 4 (1)
- CROSS-AUS Newsletter 5 (2)
- CROSS-AUS [sub-heading only] (4)
- CROSS-UK Newsletter 1 (4)
- CROSS-UK Newsletter 2 (3)
- CROSS-UK Newsletter 4 (3)
- CROSS-UK Newsletter 5 (1)
- CROSS-UK Newsletter 6 (2)
- CROSS-UK Newsletter 9 (1)
- CROSS-UK Newsletter 19 (1)
- CROSS-UK Newsletter 20 (1)
- CROSS-UK Newsletter 21 (1)
- CROSS-UK Newsletter 22 (1)
- CROSS-UK Newsletter 27 (2)
- CROSS-UK Newsletter 29 (2)
- CROSS-UK Newsletter 30 (1)
- CROSS-UK Newsletter 31 (2)
- CROSS-UK Newsletter 32 (2)
- CROSS-UK Newsletter 33 (1)
- CROSS-UK Newsletter 34 (2)
- CROSS-UK Newsletter 35 (1)
- CROSS-UK Newsletter 37 (2)
- CROSS-UK Newsletter 38 (2)
- CROSS-UK Newsletter 39 (2)
- CROSS-UK Newsletter 43 (1)
- CROSS-UK Newsletter 44 (1)
- CROSS-UK Newsletter 48 (3)
- CROSS-UK Newsletter 51 (1)
- CROSS-UK Newsletter 52 (2)
- CROSS-UK Newsletter 53 (2)
- CROSS-UK Newsletter 54 (1)
- CROSS-UK Newsletter 55 (1)
- CROSS-UK Newsletter 56 (1)
- CROSS-UK Newsletter 60 (4)
- CROSS-UK Newsletter 67 (1)
- CROSS-UK [sub-heading only] (51)
- CROSS-US Newsletter 3 (1)
- CROSS Newsletter (32)
- (-) CROSS Safety Report (87)
- News [sub-heading only] (14)
CROSS regions
Metal cladding panels fail and fall to ground
During high winds, a number of metal cladding panels failed and fell to the ground from a tall commercial building in a major UK city.
26 August 2022
CROSS Safety Report
Report ID: 1134
Region: CROSS-UK
Connection fixity considerations for steel frame modelling
This report concerns the modelling of joints when using computer programs. In some cases, engineers are applying rotational releases to joints in models but subsequently designing the connections as rigid. This leaves a fundamental mismatch between analysis and design which may lead to unsafe structural connections argues a reporter.
17 November 2022
CROSS Safety Report
Report ID: 1139
Region: CROSS-UK
Steelwork splices do not match design calculations
Remedial works had to be carried out after it was found that steelwork splices on site did not match calculations which were retrospectively provided by a contractor.
29 March 2021
CROSS Safety Report
Report ID: 916
Region: CROSS-UK
Misleading instructions for a structural component
A reporter confirms the difficulty encountered whilst endeavouring to ensure cast-in insulated connectors supporting a parapet wall and balustrade were properly fixed.
26 August 2022
CROSS Safety Report
Report ID: 1127
Region: CROSS-UK
Unsafe design of retrofit cantilever balconies
A structural assessment of a number of new balconies being added to an existing building revealed critical concerns in respect of fixings back into the existing brickwork.
26 August 2022
CROSS Safety Report
Report ID: 1128
Region: CROSS-UK
CE marking scheme for structural steelwork
Concern has been expressed about the way in which the CE marking scheme for structural steelwork will be monitored, enforced and policed in the UK, since the use of CE marking is only voluntary here (but compulsory in mainland Europe).
1 April 2007
CROSS Safety Report
Report ID: 70
Region: CROSS-UK
Balustrades in public buildings
A reporter had a concern regarding a timber balustrade in a showroom.
1 February 2007
CROSS Safety Report
Report ID: 61
Region: CROSS-UK
Liquid metal assisted cracking
Large cracks appeared down the sides of gusset welds after a truss was erected on site.
1 November 2006
CROSS Safety Report
Report ID: 49
Region: CROSS-UK
Dangerous modification to a column
A reporter was requested to visit a warehouse to inspect work carried out to a main support column that had been modified by a builder.
1 July 2010
CROSS Safety Report
Report ID: 169
Region: CROSS-UK
Fall of bridge deck support due to bolt over-tightening
A 7t steel frame designed to temporarily support part of a bridge deck during bearing refurbishments work fell from height as it was about to be lowered some 21m to the ground.
1 January 2011
CROSS Safety Report
Report ID: 216