Safety information search results
Filter your results
Products
Project or lifecycle stage
Design
Operation or occupation
Codes, standards & regulations
Fire incident response
Construction period
Method of construction
Structural form
Elements & systems
Temporary works
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Project delivery methods
Business practice
Risk management
Public incidents
Theme pages
Locations
Content type
- CROSS-UK Newsletter 2 (1)
- CROSS-UK Newsletter 19 (1)
- CROSS-UK Newsletter 20 (1)
- CROSS-UK Newsletter 26 (2)
- CROSS-UK Newsletter 28 (1)
- CROSS-UK Newsletter 36 (1)
- CROSS-UK Newsletter 41 (1)
- CROSS-UK Newsletter 42 (1)
- CROSS-UK Newsletter 45 (1)
- CROSS-UK Newsletter 52 (1)
- CROSS-UK Newsletter 54 (3)
- CROSS-UK Newsletter 55 (1)
- CROSS-UK Newsletter 56 (2)
- CROSS-UK Newsletter 58 (1)
- CROSS-UK Newsletter 59 (1)
- (-) CROSS-UK [sub-heading only] (19)
- CROSS Newsletter (10)
- CROSS Safety Report (19)
- News [sub-heading only] (5)
CROSS regions
Differing reinforcement couplers
On a recent project, because of supply problems, the contractor decided to change from the specified rebar couplers (type ‘A’) to those of another manufacturer (type ‘B’).
1 March 2006
CROSS Safety Report
Report ID: 28
Region: CROSS-UK
Effect of staff change on a design
A reporter illustrates how risk can be generated from staff turnover.
1 October 2012
CROSS Safety Report
Report ID: 277
Region: CROSS-UK
Structural assessments of multi-storey car parks
The parking industry has in recent years (2012) seen several MSCPs closed due to structural fears, says a reporter, which begs the question how close were they to structural failure before they were taken out of service?
1 April 2012
CROSS Safety Report
Report ID: 224
Region: CROSS-UK
Design deficiencies in calculations submitted to a Local Authority
A Local Authority Building Control manager has sent a list which gives twenty nine of the more serious design review queries raised by the building control structural checking process over the last five years.
1 October 2010
CROSS Safety Report
Report ID: 210
Region: CROSS-UK
Unsuitable underpinning
When reviewing a consulting engineer’s proposal to underpin a party wall, the reporter noticed that there was insufficient vertical load to maintain stability under lateral load from the retained height of soil.
1 July 2010
CROSS Safety Report
Report ID: 175
Region: CROSS-UK
Computer analysis and slab design twisting moments
A reporter has noticed on many occasions when checking reinforced concrete and post-tensioned slab designs that engineers often neglect to consider twisting moments when arriving at slab design moments.
1 October 2014
CROSS Safety Report
Report ID: 441
Region: CROSS-UK
Actively seeking to identify hazards
A reporter investigating a near miss incident raises concerns that an active prompt to seek out hazards is not being undertaken on innovative construction design and methods.
1 April 2016
CROSS Safety Report
Report ID: 530
Region: CROSS-UK
Columns missing due to 3D modelling
A new eight storey residential concrete frame building was being constructed and several columns were omitted from the ground and first floor level drawings, says a reporter.
1 January 2017
CROSS Safety Report
Report ID: 614
Region: CROSS-UK
Inadequate billets used in precast concrete connections
Whilst completing a third-party design appraisal, a correspondent found that solid steel billets intended to form the primary shear transfer mechanism between concrete beams and columns were insufficient for this purpose.
1 April 2019
CROSS Safety Report
Report ID: 705
Region: CROSS-UK
Compatibility at RC column to slab joint - strong column/weak slab
A reporter who was reviewing the structural design of a commercial building raises concerns over the compatibility at column/slab joints when different grades of concrete are used.
1 April 2012
CROSS Safety Report
Report ID: 296
Region: CROSS-UK
Submit a report
Your report will make a difference. It will help to create positive change and improve safety.