Safety information search results
Filter your results
Building height
Products
Project or lifecycle stage
Design
Operation or occupation
Codes, standards & regulations
Fire incident response
Construction period
Method of construction
Structural form
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Project delivery methods
Business practice
Public incidents
Theme pages
Locations
Content type
- CROSS-AUS Newsletter 3 (1)
- CROSS-AUS [sub-heading only] (1)
- CROSS-UK Newsletter 2 (1)
- CROSS-UK Newsletter 4 (1)
- CROSS-UK Newsletter 11 (1)
- CROSS-UK Newsletter 26 (1)
- CROSS-UK Newsletter 31 (1)
- CROSS-UK Newsletter 43 (1)
- CROSS-UK Newsletter 47 (1)
- CROSS-UK Newsletter 52 (2)
- CROSS-UK Newsletter 54 (1)
- CROSS-UK Newsletter 55 (1)
- CROSS-UK Newsletter 56 (1)
- CROSS-UK Newsletter 57 (1)
- CROSS-UK Newsletter 65 (1)
- CROSS-UK [sub-heading only] (13)
- CROSS Newsletter (8)
- CROSS Safety Report (18)
- News [sub-heading only] (5)
CROSS regions
Permanent formwork to slabs
Concerns are raised over deflection issues that are not being considered when using permanent formwork.
1 January 2011
CROSS Safety Report
Report ID: 215
Region: CROSS-UK
Compatibility at RC column to slab joint - strong column/weak slab
A reporter who was reviewing the structural design of a commercial building raises concerns over the compatibility at column/slab joints when different grades of concrete are used.
1 April 2012
CROSS Safety Report
Report ID: 296
Region: CROSS-UK
Safety issues with composite metal deck floors
A contractor had a near miss when pouring a concrete slab with permanent formwork.
1 January 2012
CROSS Safety Report
Report ID: 288
Region: CROSS-UK
Follow up to Liquid Metal Assisted Cracking (LMAC)
A recent case involving cracking around holes in large structural components was detected immediately after galvanising as a result of the team being aware of the need for post galvanising inspection.
1 July 2008
CROSS Safety Report
Report ID: 105
Region: CROSS-UK
Incorrectly installed tension control bolts could have led to serious consequences
A reporter finds incorrectly installed system HRC preload bolt assemblies, better known as tension control bolts, during a site inspection of a new highway bridge over a railway. The incorrectly fitted bolts could have had major structural implications, and led to other safety risks, if the installation error had not been spotted.
24 May 2023
CROSS Safety Report
Report ID: 1196
Region: CROSS-UK
Poor quality design leads to failure for a small design and build contract
An example of a small design and build contract where poor design and management led to an inadequate structure being built.
6 June 2022
CROSS Safety Report
Report ID: 1088
Region: CROSS-UK
Liquid metal assisted cracking (LMAC)
A reporter raises concerns about the risk of liquid metal assisted cracking during the hot dip galvanising process.
1 November 2006
CROSS Safety Report
Report ID: 45
Region: CROSS-UK
Steelwork connection design
A reporter was asked to design connections for a multi-storey building for which the frame had been designed by another engineer. The result was a near collapse situation.
1 March 2006
CROSS Safety Report
Report ID: 25
Region: CROSS-UK
Stability of tenants' mezzanine
A reporter is concerned about structures where cold-rolled sections depend upon the chipboard for their lateral torsional restraint, and to act as a horizontal diaphragm.
1 July 2013
CROSS Safety Report
Report ID: 378
Region: CROSS-UK
Inadequate billets used in precast concrete connections
Whilst completing a third-party design appraisal, a correspondent found that solid steel billets intended to form the primary shear transfer mechanism between concrete beams and columns were insufficient for this purpose.
1 April 2019
CROSS Safety Report
Report ID: 705
Region: CROSS-UK
Submit a report
Your report will make a difference. It will help to create positive change and improve safety.
Our secure and confidential safety reporting system gives professionals the opportunity to share their experiences to help others.