Safety information search results
Filter your results
Building or structure type
Materials
Products
Project or lifecycle stage
Design
Fire incident response
Project type
- Alteration & conversion project (3)
- Assessment project [sub-heading only] (5)
- Conservation & restoration project (1)
- Construction project [sub-heading only] (30)
- Demolition project (5)
- New build (21)
- Refurbishment (2)
- Remediation project (4)
- Repair project (2)
- Strengthening project (1)
- Structural assessment (8)
Method of construction
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Project delivery methods
Business practice
Locations
Content type
- CROSS-AUS Newsletter 3 (1)
- CROSS-AUS Newsletter 4 (2)
- CROSS-AUS [sub-heading only] (3)
- CROSS-UK Newsletter 2 (1)
- CROSS-UK Newsletter 3 (1)
- CROSS-UK Newsletter 4 (1)
- CROSS-UK Newsletter 6 (1)
- CROSS-UK Newsletter 9 (3)
- CROSS-UK Newsletter 12 (1)
- CROSS-UK Newsletter 18 (1)
- CROSS-UK Newsletter 20 (1)
- CROSS-UK Newsletter 26 (2)
- CROSS-UK Newsletter 28 (1)
- CROSS-UK Newsletter 30 (2)
- CROSS-UK Newsletter 31 (1)
- CROSS-UK Newsletter 35 (1)
- CROSS-UK Newsletter 36 (1)
- CROSS-UK Newsletter 38 (1)
- CROSS-UK Newsletter 39 (1)
- CROSS-UK Newsletter 41 (2)
- CROSS-UK Newsletter 45 (1)
- CROSS-UK Newsletter 54 (2)
- CROSS-UK Newsletter 58 (5)
- CROSS-UK Newsletter 59 (1)
- CROSS-UK Newsletter 60 (2)
- CROSS-UK Newsletter 68 (1)
- CROSS-UK [sub-heading only] (28)
- CROSS Newsletter (16)
- CROSS Safety Report (60)
- News [sub-heading only] (5)
CROSS regions
Design and erection of prefabricated (precast) concrete
A correspondent considers that there should always be an experienced temporary works designer for prefabricated concrete structures as many structural engineers do not consider the erection methodology when designing such structures.
1 February 2020
CROSS Safety Report
Report ID: 871
Region: CROSS-AUS
Unconservative design of flat slab due to software modelling issues
A reporter discusses how a design/modelling problem caused an under-designed reinforced concrete (RC) slab to be constructed.
1 April 2020
CROSS Safety Report
Report ID: 886
Region: CROSS-UK
Post-tensioned slab failure during tendon stressing operations
A reporter disseminates the lessons learned after the end of a slab burst while stressing the tendons in a post-tensioned concrete slab.
1 April 2020
CROSS Safety Report
Report ID: 882
Region: CROSS-UK
Missing punching shear reinforcement in concrete slabs
A reporter raises concerns of how two separate engineers observed the omission of design punching shear reinforcement prior to slab pours being undertaken on two different sites.
1 April 2020
CROSS Safety Report
Report ID: 906
Region: CROSS-UK
Emergency motorway lane closure during concrete repairs
This report highlights how confusion during concrete repair works led to an unplanned emergency lane closure of a bridge carrying a motorway.
1 July 2020
CROSS Safety Report
Report ID: 926
Region: CROSS-UK
Inadequate punching shear reinforcement in flat slabs
This report highlights how remedial works were required in a number of residential buildings after inadequate punching shear reinforcement was identified.
14 October 2020
CROSS Safety Report
Report ID: 950
Region: CROSS-UK
Overloading metal decking in temporary state
During construction of steel structures with composite metal decking floors, a reporter has observed numerous occasions when the metal decking was close to being overloaded.
1 August 2020
CROSS Safety Report
Report ID: 919
Region: CROSS-AUS
Failure of RAAC planks in schools
A reporter was asked to investigate a reinforced autoclaved aerated concrete (RAAC) roof which had collapsed in a school.
1 April 2020
CROSS Safety Report
Report ID: 908
Region: CROSS-UK, CROSS-AUS, CROSS-US
GFRP reinforcement in concrete structures
A correspondent has become aware of work being undertaken in the field of glass fibre reinforced polymer (GFRP) reinforcement as a substitute for steel rebar in concrete structures and is deeply concerned by what they have observed.
1 August 2020
CROSS Safety Report
Report ID: 939
Region: CROSS-AUS
Fire risks in multi-storey car parks
A reporter is concerned by the reluctance of the industry to voluntarily take on board and proactively react to the lessons learnt from the fire at the Echo Arena car park in Liverpool.
14 October 2020
CROSS Safety Report
Report ID: 940
Region: CROSS-UK