Safety information search results
Filter your results
Safety area
Building or structure type
Building height
Materials
Products
Project or lifecycle stage
Operation or occupation
Codes, standards & regulations
Fire incident response
Project type
Construction period
Method of construction
Structural form
Elements & systems
Temporary works
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Organisations
Project delivery methods
Business practice
Risk management
Public incidents
Theme pages
Locations
Content type
CROSS regions
Failure to grout steel frame bases
A reporter describes a problem that arose during the construction stage of a project when a steel frame supporting pipe and cable racks was loaded before the frame baseplates were grouted.
24 May 2023
CROSS Safety Report
Report ID: 1190
Region: CROSS-UK
Painted faying surfaces leads to connections with insufficient load capacity
Painted, rather than the required unpainted connection faying surfaces, were identified by the Resident Engineer of a reporter's firm during the erection of a primary frame for a large project. The painted surfaces resulted in the connections not having sufficient load carrying capacity and necessitated remedial works.
20 November 2023
CROSS Safety Report
Report ID: 896
Region: CROSS-UK