Safety information search results
Filter your results
Building height
Project or lifecycle stage
Design
Operation or occupation
Codes, standards & regulations
Fire incident response
Construction period
Method of construction
Structural form
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Project delivery methods
Business practice
Public incidents
Theme pages
Locations
Content type
- CROSS-UK Newsletter 1 (1)
- CROSS-UK Newsletter 5 (1)
- CROSS-UK Newsletter 7 (1)
- CROSS-UK Newsletter 24 (1)
- CROSS-UK Newsletter 25 (1)
- CROSS-UK Newsletter 28 (2)
- CROSS-UK Newsletter 32 (2)
- CROSS-UK Newsletter 37 (1)
- CROSS-UK Newsletter 44 (1)
- CROSS-UK Newsletter 45 (2)
- CROSS-UK Newsletter 47 (1)
- CROSS-UK Newsletter 51 (1)
- CROSS-UK Newsletter 52 (3)
- CROSS-UK Newsletter 54 (1)
- CROSS-UK Newsletter 58 (2)
- CROSS-UK Newsletter 62 (1)
- CROSS-UK [sub-heading only] (21)
- CROSS Newsletter (13)
- CROSS Safety Report (24)
- News [sub-heading only] (7)
CROSS regions
Misleading instructions for a structural component
A reporter confirms the difficulty encountered whilst endeavouring to ensure cast-in insulated connectors supporting a parapet wall and balustrade were properly fixed.
26 August 2022
CROSS Safety Report
Report ID: 1127
Region: CROSS-UK
Professional indemnity insurance issues raise safety concerns
Several reporters have raised concerns in relation to significant cost increases and the introduction of new restrictions on professional indemnity insurance (PII) policies.
13 August 2021
CROSS Safety Report
Report ID: 1022
Region: CROSS-UK
Steelwork splices do not match design calculations
Remedial works had to be carried out after it was found that steelwork splices on site did not match calculations which were retrospectively provided by a contractor.
29 March 2021
CROSS Safety Report
Report ID: 916
Region: CROSS-UK
Design of timber structures
An approximate design led to a timber roof deflecting considerably.
1 November 2005
CROSS Safety Report
Report ID: 17
Region: CROSS-UK
Responsibility for change
The inadequate substitution of lintels led to them buckling, and the surrounding masonry cracking.
1 February 2007
CROSS Safety Report
Report ID: 50
Region: CROSS-UK
Building regulations submissions
This report has been written on behalf of a group of senior local government structural engineers who refer to previous CROSS newsletters and in particular the reports relating to the poor quality of building regulation submissions and lack of checking resources.
1 July 2007
CROSS Safety Report
Report ID: 65
Region: CROSS-UK
Licensing of temporary structures
Temporary structures, such as stages, marquees, lighting towers, video screens and the like are erected at a huge number of events in the UK each year. A reporter who inspects many such structures raises concerns that the systems in place for ensuring their stability are not working.
1 January 2012
CROSS Safety Report
Report ID: 276
Region: CROSS-UK
Effect of staff change on a design
A reporter illustrates how risk can be generated from staff turnover.
1 October 2012
CROSS Safety Report
Report ID: 277
Region: CROSS-UK
Design deficiencies in long span steelwork portal
A firm commissioned to design steel joints on a large portal frame structure noticed that there was lack of restraint to a series of long span rafters.
1 October 2013
CROSS Safety Report
Report ID: 329
Region: CROSS-UK
Falsework support to a bridge – a near miss
This report follows the near collapse of a birdcage scaffold falsework structure during an 800 cubic metre concrete pour on a motorway bridge.
1 October 2012
CROSS Safety Report
Report ID: 333
Region: CROSS-UK
Submit a report
Your report will make a difference. It will help to create positive change and improve safety.