Safety information search results
Filter your results
Building or structure type
Project or lifecycle stage
Design
Fire incident response
Method of construction
Elements & systems
- Balconies (3)
- Balustrades (2)
- Beams (16)
- Bracing (8)
- Canopies (1)
- Cladding (2)
- Columns (11)
- Fasteners & connections (27)
- Fire protection (1)
- Foundations (4)
- Insulation (1)
- Light gauge steel framing (3)
- Lintels (1)
- Padstones (3)
- Parapets (1)
- PV panels (1)
- Roofs (5)
- Slabs (2)
- Trusses (1)
- Walls (5)
- Wall ties (1)
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Project delivery methods
Business practice
Public incidents
Content type
- CROSS-AUS Newsletter 1 (1)
- CROSS-AUS Newsletter 5 (1)
- CROSS-AUS [sub-heading only] (1)
- CROSS-UK Newsletter 1 (1)
- CROSS-UK Newsletter 2 (4)
- CROSS-UK Newsletter 4 (1)
- CROSS-UK Newsletter 8 (1)
- CROSS-UK Newsletter 19 (1)
- CROSS-UK Newsletter 28 (1)
- CROSS-UK Newsletter 29 (2)
- CROSS-UK Newsletter 30 (2)
- CROSS-UK Newsletter 34 (1)
- CROSS-UK Newsletter 36 (1)
- CROSS-UK Newsletter 37 (1)
- CROSS-UK Newsletter 39 (1)
- CROSS-UK Newsletter 40 (1)
- CROSS-UK Newsletter 44 (2)
- CROSS-UK Newsletter 46 (2)
- CROSS-UK Newsletter 47 (3)
- CROSS-UK Newsletter 48 (2)
- CROSS-UK Newsletter 49 (1)
- CROSS-UK Newsletter 50 (1)
- CROSS-UK Newsletter 51 (2)
- CROSS-UK Newsletter 54 (1)
- CROSS-UK Newsletter 55 (2)
- CROSS-UK Newsletter 56 (1)
- CROSS-UK Newsletter 57 (1)
- CROSS-UK Newsletter 59 (2)
- CROSS-UK Newsletter 60 (1)
- CROSS-UK Newsletter 65 (1)
- CROSS-UK [sub-heading only] (37)
- CROSS Newsletter (29)
- CROSS Safety Report (56)
- News [sub-heading only] (15)
CROSS regions
Overloading a portal frame with suspended services
A reporter designing a single storey portal frame used a standard roof service loading of 0.25kN/m2. After the project was completed, a tenant for the unit took over fit out and added a considerable amount of sprinkler pipework into the roof. This created local overloading.
21 August 2023
CROSS Safety Report
Report ID: 1195
Region: CROSS-UK
Incorrectly installed tension control bolts could have led to serious consequences
A reporter finds incorrectly installed system HRC preload bolt assemblies, better known as tension control bolts, during a site inspection of a new highway bridge over a railway. The incorrectly fitted bolts could have had major structural implications, and led to other safety risks, if the installation error had not been spotted.
24 May 2023
CROSS Safety Report
Report ID: 1196
Region: CROSS-UK
Concerns over corrosion of dissimilar metals in fixing cavity wall tie systems
A reporter is concerned about corrosion that may occur between dissimilar metals that can be used in cavity wall tie systems. The reporter has noted that stainless steel and carbon steel may be fixed together in wall cavities, which are damp environments, and that corrosion of dissimilar metals in contact may occur.
24 May 2023
CROSS Safety Report
Report ID: 1186
Region: CROSS-UK
Wrong length blind bolts lead to unsafe bridge structure
Bridge strengthening being carried out using blind bolts left a structure in an unsafe condition with traffic loading on it.
20 February 2023
CROSS Safety Report
Report ID: 1185
Region: CROSS-UK
Cantilever bridge parapet falsework failure
A reporter has experienced the failure of cantilever parapet falsework twice, for different reasons, using two different products during bridge construction.
20 February 2023
CROSS Safety Report
Report ID: 1159
Region: CROSS-UK
Steelwork delivered to site
The contractor on a domestic building project reported that there were deficiencies in steelwork supplied to site.
1 October 2007
CROSS Safety Report
Report ID: 80
Region: CROSS-UK
Post-fixed RC anchors - assumptions lead to unsafe design
A reporter raises concerns that engineers may be using post-fixed anchors without complying with the manufacturer's guidance or ensuring that their design assumptions are applicable.
1 January 2015
CROSS Safety Report
Report ID: 443
Region: CROSS-UK
Steel stud failures during bridge construction
This report concerns the failure of a steel studs during construction works on a new bridge associated with major road improvements.
1 October 2012
CROSS Safety Report
Report ID: 332
Region: CROSS-UK
Lack of experience on steel column erection
A reporter highlights how works progressed on site without a detailed method statement being provided by the contractor even though it had been requested.
1 April 2013
CROSS Safety Report
Report ID: 324
Region: CROSS-UK
Chain hoist problem
A reporter raises concerns after brand new proprietary hoists had to be returned to the manufacturer for remedial works.
1 April 2013
CROSS Safety Report
Report ID: 317