Combination load cases in proprietary software cause concern
A reporter is concerned about a widely used software package that does not, in their opinion, generate load combinations in accordance with the Eurocodes being followed.
18 October 2023
CROSS Safety Report
Report ID: 1170
Region: CROSS-UK
Concerns over corrosion of dissimilar metals in fixing cavity wall tie systems
A reporter is concerned about corrosion that may occur between dissimilar metals that can be used in cavity wall tie systems. The reporter has noted that stainless steel and carbon steel may be fixed together in wall cavities, which are damp environments, and that corrosion of dissimilar metals in contact may occur.
24 May 2023
CROSS Safety Report
Report ID: 1186
Region: CROSS-UK
Poorly applied external insulation on buildings
This report concerns external insulation on buildings being inadequately applied and fixed, with poor control of the workmanship standards, leading to potential safety concerns and damage to the property.
21 August 2023
CROSS Safety Report
Report ID: 1203
Region: CROSS-UK
Incorrectly installed tension control bolts could have led to serious consequences
A reporter finds incorrectly installed system HRC preload bolt assemblies, better known as tension control bolts, during a site inspection of a new highway bridge over a railway. The incorrectly fitted bolts could have had major structural implications, and led to other safety risks, if the installation error had not been spotted.
24 May 2023
CROSS Safety Report
Report ID: 1196
Region: CROSS-UK
'Design' for alterations to a dwelling carried out by an unsuitable person
A reporter was called upon to review a design for the removal of a loadbearing wall during the refurbishment of a residence. A builder was already on site but had stopped work since they considered the engineering design to be unsatisfactory and the structural designer was not responding to their queries. The reporter found that the structural design being followed was far from competent.
21 August 2023
CROSS Safety Report
Report ID: 1236
Region: CROSS-UK
Building regulations submissions
This report has been written on behalf of a group of senior local government structural engineers who refer to previous CROSS newsletters and in particular the reports relating to the poor quality of building regulation submissions and lack of checking resources.
1 July 2007
CROSS Safety Report
Report ID: 65