Safety information search results
Filter your results
Building or structure type
Materials
Project or lifecycle stage
Design
Operation or occupation
Codes, standards & regulations
Fire incident response
Construction period
Method of construction
Structural form
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Project delivery methods
Business practice
Public incidents
Locations
Content type
- CROSS-AUS Newsletter 1 (1)
- CROSS-AUS [sub-heading only] (1)
- CROSS-UK Newsletter 1 (1)
- CROSS-UK Newsletter 2 (2)
- CROSS-UK Newsletter 3 (1)
- CROSS-UK Newsletter 4 (3)
- CROSS-UK Newsletter 5 (1)
- CROSS-UK Newsletter 6 (2)
- CROSS-UK Newsletter 8 (2)
- CROSS-UK Newsletter 12 (1)
- CROSS-UK Newsletter 13 (2)
- CROSS-UK Newsletter 14 (1)
- CROSS-UK Newsletter 16 (1)
- CROSS-UK Newsletter 17 (2)
- CROSS-UK Newsletter 19 (2)
- CROSS-UK Newsletter 21 (1)
- CROSS-UK Newsletter 22 (2)
- CROSS-UK Newsletter 24 (1)
- CROSS-UK Newsletter 25 (1)
- CROSS-UK Newsletter 28 (2)
- CROSS-UK Newsletter 29 (1)
- CROSS-UK Newsletter 30 (3)
- CROSS-UK Newsletter 31 (3)
- CROSS-UK Newsletter 32 (2)
- CROSS-UK Newsletter 34 (3)
- CROSS-UK Newsletter 35 (2)
- CROSS-UK Newsletter 37 (1)
- CROSS-UK Newsletter 38 (1)
- CROSS-UK Newsletter 39 (2)
- CROSS-UK Newsletter 40 (1)
- CROSS-UK Newsletter 41 (1)
- CROSS-UK Newsletter 42 (2)
- CROSS-UK Newsletter 43 (2)
- CROSS-UK Newsletter 44 (3)
- CROSS-UK Newsletter 45 (1)
- CROSS-UK Newsletter 46 (2)
- CROSS-UK Newsletter 51 (1)
- CROSS-UK Newsletter 52 (2)
- CROSS-UK Newsletter 53 (1)
- CROSS-UK Newsletter 54 (1)
- CROSS-UK Newsletter 55 (2)
- CROSS-UK Newsletter 56 (2)
- CROSS-UK Newsletter 57 (1)
- CROSS-UK Newsletter 58 (1)
- CROSS-UK Newsletter 59 (1)
- CROSS-UK Newsletter 62 (2)
- CROSS-UK Newsletter 65 (1)
- CROSS-UK Newsletter 67 (1)
- CROSS-UK [sub-heading only] (66)
- CROSS Newsletter (39)
- CROSS Safety Report (99)
- CROSS Topic Paper (2)
- News [sub-heading only] (12)
- Safety information from CROSS [sub-heading only] (1)
CROSS regions
Object rolling into live carriageway
A disc of concrete rolled from a construction area onto a live carriageway, colliding with a passing vehicle.
6 June 2022
Report ID: 1089
Region: CROSS-UK
Tower crane base designs
A reporter’s firm has been involved in the design and checking of numerous tower crane bases and have come across many examples where the supplier of the tower crane has supplied incorrect loadings. These incorrect loadings could have led to crane failures had the errors not been spotted.
7 June 2022
CROSS Safety Report
Report ID: 1093
Region: CROSS-UK
Control of temporary works excavation
Poor, high-water content excavated material, slipped into a 15-20m deep borrow pit. The material had slipped to the bottom of the pit partially burying excavation, crushing and screening equipment. If this slip had occurred during working hours, the impact could have been very serious.
17 November 2022
CROSS Safety Report
Report ID: 1146
Region: CROSS-UK
Cantilever bridge parapet falsework failure
A reporter has experienced the failure of cantilever parapet falsework twice, for different reasons, using two different products during bridge construction.
20 February 2023
CROSS Safety Report
Report ID: 1159
Region: CROSS-UK
Questionable temporary works used to retain embankment excavation
This report is about the need for properly engineered retaining walls for all heights of retained materials.
1 June 2022
CROSS Safety Report
Report ID: 806
Region: CROSS-UK
Temporary instability of columns
Concerns were raised by a reporter on the temporary stability of concrete columns during construction.
2 February 2023
CROSS Safety Report
Report ID: 872
Region: CROSS-UK
Incorrect lifting system used for precast concrete stair elements
A reporter was asked to inspect a precast concrete stair unit which was exhibiting cracking around the lifting anchor locations after being de-moulded.
13 December 2022
CROSS Safety Report
Report ID: 883
Region: CROSS-UK
Tower crane bases
A reporter came across a situation in which one of the anchors into a concrete crane base appeared to be loose.
5 September 2022
CROSS Safety Report
Report ID: 973
Region: CROSS-UK
Architectural panel acting as barrier
A reporter came across a scenario on site where an architectural decorative panel was acting as a barrier during the construction stage without being designed to act as one.
6 April 2023
CROSS Safety Report
Report ID: 927
Region: CROSS-UK
Inadequate temporary works on domestic project
An example of inadequate temporary works on a project, and problems reporting the safety issue to the authorities.
14 December 2021
CROSS Safety Report
Report ID: 1044
Region: CROSS-UK
Submit a report
Your report will make a difference. It will help to create positive change and improve safety.
Our secure and confidential safety reporting system gives professionals the opportunity to share their experiences to help others.