Final report of the Advisory Committee on Falsework (Bragg report)
This Her Majesty's Stationery Office (HMSO) report, better known as the Bragg report, published in 1975, set requirements for erection and stability of these temporary structures.
1 January 1975
Third party content
Publisher: Health and Safety Executive (HSE)
Failure of cast-in wire lifting loops on manhole cover slabs
A cast-in wire lifting loop failed when lifting a 4m diameter precast manhole cover slab into place.
23 May 2022
CROSS Safety Report
Report ID: 629
Region: CROSS-UK
Slipform temporary works design
A reporter was performing a CAT III check on a 14 storey slipform design when they discovered that the temporary works design was inadequate.
5 September 2022
CROSS Safety Report
Report ID: 809
Region: CROSS-UK
Trench sheet naming confusion
A reporter involved with temporary works design has been made aware that there are two suppliers providing a trench sheet under the same name.
30 June 2022
CROSS Safety Report
Report ID: 814
Region: CROSS-UK
Stress fracture on temporary compact stairs
A stress fracture to a temporary access compact stair unit was identified on site by a scaffold manager.
19 March 2023
CROSS Safety Report
Report ID: 805
Region: CROSS-UK
Questionable temporary works used to retain embankment excavation
This report is about the need for properly engineered retaining walls for all heights of retained materials.
1 June 2022
CROSS Safety Report
Report ID: 806
Region: CROSS-UK
Accidental partial demolition of a beam
During a site visit, the permanent works design engineer noticed that hydro-demolition of the end of a floor supporting beam had taken place out of sequence. This introduced a pattern of bending moments and shear forces that were not considered in the original design.
6 April 2023
CROSS Safety Report
Report ID: 855
Region: CROSS-UK
Temporary instability of columns
Concerns were raised by a reporter on the temporary stability of concrete columns during construction.
2 February 2023
CROSS Safety Report
Report ID: 872
Region: CROSS-UK
Architectural panel acting as barrier
A reporter came across a scenario on site where an architectural decorative panel was acting as a barrier during the construction stage without being designed to act as one.
6 April 2023
CROSS Safety Report
Report ID: 927
Region: CROSS-UK
Incorrect lifting system used for precast concrete stair elements
A reporter was asked to inspect a precast concrete stair unit which was exhibiting cracking around the lifting anchor locations after being de-moulded.
13 December 2022
CROSS Safety Report
Report ID: 883
Region: CROSS-UK
Submit a report
Your report will make a difference. It will help to create positive change and improve safety.
Our secure and confidential safety reporting system gives professionals the opportunity to share their experiences to help others.