Content type
- CROSS-AUS Newsletter 2 (1)
- CROSS-AUS Newsletter 3 (1)
- CROSS-AUS [sub-heading only] (2)
- CROSS-UK Newsletter 54 (1)
- CROSS-UK Newsletter 57 (1)
- CROSS-UK Newsletter 58 (1)
- CROSS-UK Newsletter 65 (3)
- CROSS-UK Newsletter 67 (1)
- CROSS-UK [sub-heading only] (3)
- CROSS-US Newsletter 1 (1)
- CROSS-US [sub-heading only] (1)
- CROSS Newsletter (2)
- CROSS Safety Report (12)
- News [sub-heading only] (1)
CROSS regions
Poor quality design leads to failure for a small design and build contract
An example of a small design and build contract where poor design and management led to an inadequate structure being built.
6 June 2022
CROSS Safety Report
Report ID: 1088
Region: CROSS-UK
Dangerous building work on domestic project
Temporary propping fails during works to a semi-detached property putting the whole building at risk of collapse.
10 March 2022
CROSS Safety Report
Report ID: 1062
Region: CROSS-UK
Water ingress to cross-laminated timber structural frame
In an eight year old building that included cross-laminated timber construction, it was found that water penetration had caused parts of the structure to rot.
6 June 2022
CROSS Safety Report
Report ID: 1124
Region: CROSS-UK
Inadequate design for basement works
An inadequate structural design for alterations to a basement led to structural distress within a substantial five-storey townhouse.
21 November 2022
CROSS Safety Report
Report ID: 1132
Region: CROSS-UK
Concerns over corrosion of dissimilar metals in fixing cavity wall tie systems
A reporter is concerned about corrosion that may occur between dissimilar metals that can be used in cavity wall tie systems. The reporter has noted that stainless steel and carbon steel may be fixed together in wall cavities, which are damp environments, and that corrosion of dissimilar metals in contact may occur.
24 May 2023
CROSS Safety Report
Report ID: 1186
Region: CROSS-UK
Concerns over robustness of some 20 year old buildings
Concerns about the robustness of several two-storey buildings dating from the early 2000s.
6 June 2022
CROSS Safety Report
Report ID: 1051
Region: CROSS-UK
Wall tie design between masonry panels and timber frames
This report discusses the potential for failure of timber frame wall ties between masonry and timber in moderate to high wind conditions.
1 January 2020
CROSS Safety Report
Report ID: 832
Region: CROSS-UK
Safety concern about the design of thin concrete walls
The reporter raises their concern about the design of thin concrete load-bearing walls, sometimes supporting 10 or more storeys.
1 July 2019
CROSS Safety Report
Report ID: 815
Region: CROSS-AUS
Unconservative design of flat slab due to software modelling issues
A reporter discusses how a design/modelling problem caused an under-designed reinforced concrete (RC) slab to be constructed.
1 April 2020
CROSS Safety Report
Report ID: 886
Region: CROSS-UK
Design and erection of prefabricated (precast) concrete
A correspondent considers that there should always be an experienced temporary works designer for prefabricated concrete structures as many structural engineers do not consider the erection methodology when designing such structures.
1 February 2020
CROSS Safety Report
Report ID: 871
Region: CROSS-AUS
Submit a report
Your report will make a difference. It will help to create positive change and improve safety.
Our secure and confidential safety reporting system gives professionals the opportunity to share their experiences to help others.