Safety information search results
Filter your results
Building or structure type
Project or lifecycle stage
Design
Operation or occupation
Fire incident response
Method of construction
Structural form
Elements & systems
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Project delivery methods
Business practice
Locations
Content type
- CROSS-AUS Newsletter 1 (2)
- CROSS-AUS [sub-heading only] (2)
- CROSS-UK Newsletter 2 (2)
- CROSS-UK Newsletter 6 (1)
- CROSS-UK Newsletter 8 (1)
- CROSS-UK Newsletter 12 (1)
- CROSS-UK Newsletter 17 (2)
- CROSS-UK Newsletter 19 (2)
- CROSS-UK Newsletter 21 (1)
- CROSS-UK Newsletter 24 (1)
- CROSS-UK Newsletter 26 (1)
- CROSS-UK Newsletter 28 (1)
- CROSS-UK Newsletter 29 (2)
- CROSS-UK Newsletter 30 (2)
- CROSS-UK Newsletter 34 (1)
- CROSS-UK Newsletter 36 (1)
- CROSS-UK Newsletter 37 (5)
- CROSS-UK Newsletter 39 (1)
- CROSS-UK Newsletter 40 (1)
- CROSS-UK Newsletter 44 (2)
- CROSS-UK Newsletter 45 (1)
- CROSS-UK Newsletter 46 (2)
- CROSS-UK Newsletter 47 (1)
- CROSS-UK Newsletter 48 (1)
- CROSS-UK Newsletter 51 (1)
- CROSS-UK Newsletter 54 (1)
- CROSS-UK Newsletter 55 (2)
- CROSS-UK Newsletter 56 (2)
- CROSS-UK Newsletter 57 (1)
- CROSS-UK Newsletter 58 (3)
- CROSS-UK Newsletter 60 (1)
- CROSS-UK Newsletter 65 (1)
- CROSS-UK [sub-heading only] (42)
- CROSS Newsletter (26)
- CROSS Safety Report (56)
- News [sub-heading only] (11)
CROSS regions
Inadequate foundation reinforcement
Subcontractors carrying out the ground works for a multi-storey development failed to provide sufficient continuity reinforcement in the ground beams.
1 October 2008
CROSS Safety Report
Report ID: 112
Region: CROSS-UK
Temporary works propping
A reporter raises concerns about the adequacy of temporary works that were installed on site during the refurbishing of a large office building.
1 January 2010
CROSS Safety Report
Report ID: 146
Region: CROSS-UK
Concerns on stability require prompt action
A reporter was concerned about overall building stability during an extension and conversion project.
1 January 2010
CROSS Safety Report
Report ID: 171
Region: CROSS-UK
Dangerous modification to a column
A reporter was requested to visit a warehouse to inspect work carried out to a main support column that had been modified by a builder.
1 July 2010
CROSS Safety Report
Report ID: 169
Region: CROSS-UK
Safety issues with composite metal deck floors
A contractor had a near miss when pouring a concrete slab with permanent formwork.
1 January 2012
CROSS Safety Report
Report ID: 288
Region: CROSS-UK
Effect of staff change on a design
A reporter illustrates how risk can be generated from staff turnover.
1 October 2012
CROSS Safety Report
Report ID: 277
Region: CROSS-UK
Documentation for imported large diameter steel pins
A reporter raises concerns over the possibility that foreign steel with poor, confusing or misleading documentation, is being used on safety critical structures in the UK.
1 January 2013
CROSS Safety Report
Report ID: 299
Region: CROSS-UK
Lack of experience on steel column erection
A reporter highlights how works progressed on site without a detailed method statement being provided by the contractor even though it had been requested.
1 April 2013
CROSS Safety Report
Report ID: 324
Region: CROSS-UK
Chain hoist problem
A reporter raises concerns after brand new proprietary hoists had to be returned to the manufacturer for remedial works.
1 April 2013
CROSS Safety Report
Report ID: 317
Region: CROSS-UK
Missing rebar identified prior to concrete slab pour
A reporter describes how they often encounter issues such as missing reinforcement while carrying out pre-pour inspections.
1 January 2013
CROSS Safety Report
Report ID: 310
Region: CROSS-UK