Safety information search results
Filter your results
Project or lifecycle stage
Design
Operation or occupation
Codes, standards & regulations
Fire incident response
Construction period
Method of construction
Temporary works
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Organisations
Project delivery methods
Business practice
Risk management
Public incidents
Theme pages
Locations
Content type
- CROSS-UK Newsletter 20 (1)
- CROSS-UK Newsletter 28 (1)
- CROSS-UK Newsletter 37 (1)
- CROSS-UK Newsletter 45 (1)
- CROSS-UK Newsletter 48 (1)
- CROSS-UK Newsletter 51 (1)
- CROSS-UK Newsletter 52 (1)
- CROSS-UK Newsletter 54 (1)
- CROSS-UK Newsletter 58 (2)
- CROSS-UK Newsletter 64 (1)
- CROSS-UK Newsletter 68 (1)
- CROSS-UK [sub-heading only] (10)
- CROSS Newsletter (8)
- CROSS Safety Report (13)
- News [sub-heading only] (1)
CROSS regions
Columns missing due to 3D modelling
A new eight storey residential concrete frame building was being constructed and several columns were omitted from the ground and first floor level drawings, says a reporter.
1 January 2017
CROSS Safety Report
Report ID: 614
Region: CROSS-UK
Inadequate end bearings for transfer beams
Whilst advising a steel fabricator on tendering for a transfer structure steel frame, a reporter's firm noticed a serious design error with the bearing pressures at the supports of a transfer beam.
1 October 2017
CROSS Safety Report
Report ID: 644
Region: CROSS-UK
Tower crane foundation design error
Whilst carrying out an independent design check on a tower crane foundation design, a reporter discovered that the piles used on site did not have the required tension capacity.
1 July 2018
CROSS Safety Report
Report ID: 662
Region: CROSS-UK