Safety information search results
Filter your results
Building or structure type
Project or lifecycle stage
Design
Codes, standards & regulations
Fire incident response
Project type
- Alteration & conversion project (2)
- Assessment project [sub-heading only] (6)
- Construction project [sub-heading only] (34)
- Demolition project (4)
- Excavation (5)
- Extension project (2)
- Fire safety assessment (2)
- Groundworks project (1)
- New build (16)
- Refurbishment (2)
- Remediation project (1)
- Repair project (1)
- Strengthening project (1)
- Structural assessment (6)
Construction period
Method of construction
Structural form
Elements & systems
Plant & equipment
Utilities
Safety reporting
Organisations
Project delivery methods
Business practice
Public incidents
Locations
Content type
- CROSS-AUS Newsletter 2 (2)
- CROSS-AUS Newsletter 3 (1)
- CROSS-AUS Newsletter 4 (1)
- CROSS-AUS Newsletter 5 (3)
- CROSS-AUS [sub-heading only] (3)
- CROSS-UK Newsletter 2 (1)
- CROSS-UK Newsletter 4 (1)
- CROSS-UK Newsletter 7 (2)
- CROSS-UK Newsletter 8 (2)
- CROSS-UK Newsletter 14 (2)
- CROSS-UK Newsletter 16 (1)
- CROSS-UK Newsletter 22 (2)
- CROSS-UK Newsletter 28 (2)
- CROSS-UK Newsletter 30 (3)
- CROSS-UK Newsletter 33 (2)
- CROSS-UK Newsletter 36 (2)
- CROSS-UK Newsletter 40 (1)
- CROSS-UK Newsletter 42 (3)
- CROSS-UK Newsletter 46 (1)
- CROSS-UK Newsletter 47 (1)
- CROSS-UK Newsletter 48 (1)
- CROSS-UK Newsletter 49 (1)
- CROSS-UK Newsletter 50 (1)
- CROSS-UK Newsletter 51 (1)
- CROSS-UK Newsletter 52 (1)
- CROSS-UK Newsletter 53 (1)
- CROSS-UK Newsletter 56 (3)
- CROSS-UK Newsletter 57 (3)
- CROSS-UK Newsletter 58 (1)
- CROSS-UK Newsletter 59 (1)
- CROSS-UK Newsletter 62 (3)
- CROSS-UK Newsletter 67 (2)
- CROSS-UK [sub-heading only] (38)
- CROSS-US Newsletter 3 (3)
- CROSS Newsletter (19)
- (-) CROSS Safety Report (69)
- News [sub-heading only] (9)
- Safety information from CROSS [sub-heading only] (1)
- Safety information [sub-heading only] (1)
CROSS regions
Collapse of brick arch overbridge during demolition
A reporter describes a project where a flanking brick arch collapsed during the demolition of two multi-span bridges over rail lines.
30 June 2022
CROSS Safety Report
Report ID: 573
Region: CROSS-UK
Concerns over execution class categorisation of steel pedestrian bridge
A reporter is concerned in respect of the steelwork execution class, and quality management arrangements, applied to the construction of a public access pedestrian bridge.
21 November 2022
CROSS Safety Report
Report ID: 1149
Region: CROSS-UK
Precast concrete demolition
During the demolition of a tower block, a column collapsed unexpectedly.
1 March 2006
CROSS Safety Report
Report ID: 27
Region: CROSS-UK
Building regulations checking
A reporter’s firm has been carrying out building regulations checks for 25 years, but it is only in the last six or seven years (say 2000-2006) that concerns have arisen, some of which are described below.
1 July 2007
CROSS Safety Report
Report ID: 33
Region: CROSS-UK
Very slender props
A reporter noticed prop that did not have ties installed while carrying out a site inspection.
1 July 2007
CROSS Safety Report
Report ID: 34
Region: CROSS-UK
Grouting of joints between load-bearing prefabricated concrete members
This report highlights the risk of failure if grouted joints between load-bearing prefabricated concrete members are not designed and installed correctly.
30 April 2021
CROSS Safety Report
Report ID: 961
Region: CROSS-AUS
Professional indemnity insurance issues raise safety concerns
Several reporters have raised concerns in relation to significant cost increases and the introduction of new restrictions on professional indemnity insurance (PII) policies.
13 August 2021
CROSS Safety Report
Report ID: 1022
Region: CROSS-UK
Use of temporary barriers to control access to hazards
This report highlights the risks associated with the use of temporary barriers to control access to unsafe workplaces. It discusses the issues when scaffolding is used as a barrier, and that this should only be considered for use as a short-term temporary barrier.
25 November 2021
CROSS Safety Report
Report ID: 980
Region: CROSS-AUS
Unsafe excavation practices
A builder undermined the existing footing of a masonry wall without being aware of the risks.
30 July 2021
CROSS Safety Report
Report ID: 1026
Region: CROSS-UK
Failures of cold formed steel floor systems during construction
This report describes numerous collapses during construction of cold formed steel floor systems caused by lack of bracing/fastening and overloading of an incomplete structure.
10 May 2021
CROSS Safety Report
Report ID: 997
Region: CROSS-US
Submit a report