Safety information search results
Filter your results
Building height
Materials
Products
Project or lifecycle stage
Operation or occupation
Codes, standards & regulations
Fire incident response
Construction period
Method of construction
Structural form
Elements & systems
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Organisations
Project delivery methods
Business practice
Public incidents
Theme pages
Locations
CROSS regions
Control of temporary works excavation
Poor, high-water content excavated material, slipped into a 15-20m deep borrow pit. The material had slipped to the bottom of the pit partially burying excavation, crushing and screening equipment. If this slip had occurred during working hours, the impact could have been very serious.
17 November 2022
CROSS Safety Report
Report ID: 1146
Region: CROSS-UK
Lack of experience on steel column erection
A reporter highlights how works progressed on site without a detailed method statement being provided by the contractor even though it had been requested.
1 April 2013
CROSS Safety Report
Report ID: 324
Region: CROSS-UK
Lack of method statements on domestic projects
A reporter has observed that where an opening is being formed on domestic properties for, say a rear extension, that the builders tend to remove the masonry and follow up with the temporary propping.
1 January 2019
CROSS Safety Report
Report ID: 757
Region: CROSS-UK
Submit a report
Your report will make a difference. It will help to create positive change and improve safety.
Our secure and confidential safety reporting system gives professionals the opportunity to share their experiences to help others.