- CROSS-AUS Newsletter 1 (1)
- CROSS-AUS [sub-heading only] (1)
- CROSS-UK Newsletter 2 (1)
- CROSS-UK Newsletter 39 (1)
- CROSS-UK Newsletter 41 (1)
- CROSS-UK Newsletter 44 (3)
- CROSS-UK Newsletter 45 (2)
- CROSS-UK Newsletter 46 (3)
- CROSS-UK Newsletter 50 (1)
- CROSS-UK Newsletter 54 (1)
- CROSS-UK Newsletter 60 (1)
- CROSS-UK [sub-heading only] (14)
- (-) CROSS Newsletter (14)
- CROSS Safety Report (14)
- (-) News [sub-heading only] (14)
CROSS regions
Steelwork connection design
A reporter was asked to design connections for a multi-storey building for which the frame had been designed by another engineer. The result was a near collapse situation.
1 March 2006
CROSS Safety Report
Report ID: 25
Region: CROSS-UK
Inadequate structural design on industrial steel structures
A reporter's firm believes that steel structures associated with plant are being erected without a design being carried out by a structural engineer and are therefore potentially dangerous.
1 April 2019
CROSS Safety Report
Report ID: 804
Region: CROSS-UK
Roof constructed without structural input
A reporter wants to highlight the problem of builders working off plans provided by an architect or surveyor and assuming that section sizes shown on their drawings are structurally adequate.
1 January 2016
CROSS Safety Report
Report ID: 515
Region: CROSS-UK
Fabrication different from design drawings
A reporter shares their experience of how a propping design they had undertaken was fabricated and installed but not in accordance with the design drawings.
1 July 2015
CROSS Safety Report
Report ID: 513
Region: CROSS-UK
Weld de-specification without design approval
A reporter's firm was engaged as fabricators for a main contractor and asked by them to de-specify full and partial penetration butt welds and replace them with fillet welds without approval from the main design engineer.
14 October 2020
CROSS Safety Report
Report ID: 845
Region: CROSS-UK
Padstones out of position leads to collapse
This report concerns the partial collapse of a terrace of four storey houses during construction due to padstones being placed incorrectly.
1 April 2017
CROSS Safety Report
Report ID: 602
Region: CROSS-UK
Columns missing due to 3D modelling
A new eight storey residential concrete frame building was being constructed and several columns were omitted from the ground and first floor level drawings, says a reporter.
1 January 2017
CROSS Safety Report
Report ID: 614
Region: CROSS-UK
Changes in temporary works scheme
Changes in the construction programme on site led to the construction of the superstructure of a building, without the liner wall below it being completed.
1 April 2017
CROSS Safety Report
Report ID: 603
Region: CROSS-UK
Heritage balustrade complying with current regulations
A reporter is hoping that CROSS might be able to help with some research for a heritage project.
1 January 2017
CROSS Safety Report
Report ID: 599
Region: CROSS-UK
Settlement of driven piles
A railway platform was constructed on piled foundations and it was noticed that one pair of piles and their associated cross head settled soon afterwards.
1 April 2017
CROSS Safety Report
Report ID: 607
Region: CROSS-UK
Submit a report
Your report will make a difference. It will help to create positive change and improve safety.
Our secure and confidential safety reporting system gives professionals the opportunity to share their experiences to help others.