Safety information search results
Filter your results
Building or structure type
Building height
Products
Project or lifecycle stage
Operation or occupation
Codes, standards & regulations
Fire incident response
Construction period
Method of construction
Structural form
Temporary works
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Project delivery methods
Business practice
Risk management
Public incidents
Theme pages
Locations
CROSS regions
Poor quality design leads to failure for a small design and build contract
An example of a small design and build contract where poor design and management led to an inadequate structure being built.
6 June 2022
CROSS Safety Report
Report ID: 1088
Region: CROSS-UK
Failure of cantilevered stone staircase
During the renovation and change-of-use conversion of a former minor stately home built around 1830, under pedestrian loading, a ‘cantilevered’ stone staircase partially collapsed without warning.
21 February 2023
CROSS Safety Report
Report ID: 1147
Region: CROSS-UK
Wall tie design between masonry panels and timber frames
This report discusses the potential for failure of timber frame wall ties between masonry and timber in moderate to high wind conditions.
1 January 2020
CROSS Safety Report
Report ID: 832
Region: CROSS-UK
Repeating the same design mistakes
A correspondent who investigates engineering failures has shared common errors which engineers keep repeating.
1 October 2019
CROSS Safety Report
Report ID: 858
Region: CROSS-UK
Cantilevered brickwork - fatal collapse during construction
A blade of 270mm cavity brickwork in a temporary condition fell and killed a bricklayer after sixteen scaffold planks were leant against the wall on the side remote from the bricklayer.
1 April 2015
CROSS Safety Report
Report ID: 476
Region: CROSS-UK
Structural issues with cladding
A reporter who investigates cladding failures shares common issues they have encountered.
1 April 2020
CROSS Safety Report
Report ID: 904
Region: CROSS-UK
Scaffold support overturns
A 5m high support scaffold screened with fabric overturned when airflow was introduced to a building.
1 January 2017
CROSS Safety Report
Report ID: 575
Region: CROSS-UK
Submit a report
Your report will make a difference. It will help to create positive change and improve safety.
Our secure and confidential safety reporting system gives professionals the opportunity to share their experiences to help others.