Safety information search results
Filter your results
Products
Project or lifecycle stage
Design
Operation or occupation
Codes, standards & regulations
Fire incident response
Construction period
Method of construction
Structural form
Elements & systems
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Project delivery methods
Business practice
Risk management
Public incidents
Theme pages
Locations
Content type
- CROSS-AUS Newsletter 3 (1)
- CROSS-AUS Newsletter 4 (1)
- CROSS-AUS [sub-heading only] (2)
- CROSS-UK Newsletter 2 (1)
- CROSS-UK Newsletter 9 (1)
- CROSS-UK Newsletter 26 (1)
- CROSS-UK Newsletter 28 (1)
- CROSS-UK Newsletter 36 (1)
- CROSS-UK Newsletter 48 (1)
- CROSS-UK Newsletter 52 (1)
- CROSS-UK Newsletter 54 (1)
- CROSS-UK Newsletter 55 (1)
- CROSS-UK Newsletter 56 (1)
- CROSS-UK Newsletter 59 (1)
- CROSS-UK Newsletter 60 (1)
- CROSS-UK [sub-heading only] (10)
- CROSS Newsletter (9)
- CROSS Safety Report (14)
- News [sub-heading only] (2)
CROSS regions
Concrete half joints
Poor reinforcement detailing and installation in a half joint led to the collapse of a series of beams and precast concrete slabs.
1 January 2008
CROSS Safety Report
Report ID: 88
Region: CROSS-UK
Steelwork connection design
A reporter was asked to design connections for a multi-storey building for which the frame had been designed by another engineer. The result was a near collapse situation.
1 March 2006
CROSS Safety Report
Report ID: 25
Region: CROSS-UK
Effect of staff change on a design
A reporter illustrates how risk can be generated from staff turnover.
1 October 2012
CROSS Safety Report
Report ID: 277
Region: CROSS-UK
Compatibility at RC column to slab joint - strong column/weak slab
A reporter who was reviewing the structural design of a commercial building raises concerns over the compatibility at column/slab joints when different grades of concrete are used.
1 April 2012
CROSS Safety Report
Report ID: 296
Region: CROSS-UK
Retaining wall excavation collapse
A 6m deep excavation formed for constructing a retaining wall on a domestic project collapsed due to insufficient propping.
1 July 2019
CROSS Safety Report
Report ID: 800
Region: CROSS-UK
Quality of design and construction of a major bridge structure
This report concerns the design and installation of the bridge bearing zones on a new prestressed precast concrete viaduct.
1 October 2018
CROSS Safety Report
Report ID: 781
Region: CROSS-UK
Repeating the same design mistakes
A correspondent who investigates engineering failures has shared common errors which engineers keep repeating.
1 October 2019
CROSS Safety Report
Report ID: 858
Region: CROSS-UK
Computer analysis and slab design twisting moments
A reporter has noticed on many occasions when checking reinforced concrete and post-tensioned slab designs that engineers often neglect to consider twisting moments when arriving at slab design moments.
1 October 2014
CROSS Safety Report
Report ID: 441
Region: CROSS-UK
Fire protection of mixed hot/cold rolled steel structure
This report describes how a high-rise building had to be remediated after it was found there was insufficient fire protection encasement of structural elements.
1 July 2020
CROSS Safety Report
Report ID: 921
Region: CROSS-UK
Design and erection of prefabricated (precast) concrete
A correspondent considers that there should always be an experienced temporary works designer for prefabricated concrete structures as many structural engineers do not consider the erection methodology when designing such structures.
1 February 2020
CROSS Safety Report
Report ID: 871
Region: CROSS-AUS
Submit a report
Your report will make a difference. It will help to create positive change and improve safety.
Our secure and confidential safety reporting system gives professionals the opportunity to share their experiences to help others.