Safety information search results
Filter your results
Building or structure type
Materials
Project or lifecycle stage
Design
Operation or occupation
Fire incident response
Project type
- Alteration & conversion project (7)
- Assessment project [sub-heading only] (1)
- Construction project [sub-heading only] (50)
- Demolition project (3)
- Excavation (1)
- Extension project (5)
- Groundworks project (1)
- New build (33)
- Refurbishment (3)
- Remediation project (4)
- Strengthening project (2)
- Structural assessment (1)
- Underpinning project (2)
Method of construction
Structural form
Elements & systems
Plant & equipment
Weather & natural hazards
Utilities
Safety reporting
Project delivery methods
Business practice
Locations
Content type
- CROSS-AUS Newsletter 1 (2)
- CROSS-AUS [sub-heading only] (2)
- CROSS-UK Newsletter 2 (2)
- CROSS-UK Newsletter 4 (1)
- CROSS-UK Newsletter 6 (1)
- CROSS-UK Newsletter 8 (1)
- CROSS-UK Newsletter 12 (1)
- CROSS-UK Newsletter 14 (1)
- CROSS-UK Newsletter 17 (2)
- CROSS-UK Newsletter 19 (2)
- CROSS-UK Newsletter 20 (1)
- CROSS-UK Newsletter 21 (1)
- CROSS-UK Newsletter 24 (1)
- CROSS-UK Newsletter 26 (1)
- CROSS-UK Newsletter 28 (1)
- CROSS-UK Newsletter 29 (2)
- CROSS-UK Newsletter 30 (2)
- CROSS-UK Newsletter 33 (1)
- CROSS-UK Newsletter 34 (1)
- CROSS-UK Newsletter 35 (1)
- CROSS-UK Newsletter 36 (1)
- CROSS-UK Newsletter 37 (5)
- CROSS-UK Newsletter 39 (1)
- CROSS-UK Newsletter 40 (2)
- CROSS-UK Newsletter 44 (2)
- CROSS-UK Newsletter 45 (2)
- CROSS-UK Newsletter 46 (2)
- CROSS-UK Newsletter 47 (1)
- CROSS-UK Newsletter 48 (1)
- CROSS-UK Newsletter 51 (1)
- CROSS-UK Newsletter 54 (1)
- CROSS-UK Newsletter 55 (2)
- CROSS-UK Newsletter 56 (3)
- CROSS-UK Newsletter 57 (1)
- CROSS-UK Newsletter 58 (3)
- CROSS-UK Newsletter 60 (2)
- CROSS-UK Newsletter 65 (1)
- CROSS-UK [sub-heading only] (50)
- CROSS Newsletter (31)
- (-) CROSS Safety Report (69)
- News [sub-heading only] (13)
CROSS regions
Poor quality design leads to failure for a small design and build contract
An example of a small design and build contract where poor design and management led to an inadequate structure being built.
6 June 2022
CROSS Safety Report
Report ID: 1088
Region: CROSS-UK
Unsafe instructions from a building inspector
On the site for an extension to a domestic property, a building inspector instructed a contractor to excavate a deep trench. The trench was in front of the neighbour's adjacent boundary retaining wall, and left a deep vertical face under the house being extended.
10 March 2022
CROSS Safety Report
Report ID: 1086
Region: CROSS-UK
Steelwork splices do not match design calculations
Remedial works had to be carried out after it was found that steelwork splices on site did not match calculations which were retrospectively provided by a contractor.
29 March 2021
CROSS Safety Report
Report ID: 916
Region: CROSS-UK
Structural steel - reinforced concrete interface
A reporter describes how the substructure of a building was constructed out of position to the extent that the steel frame could not be erected to tolerance and could not be connected to the holding down bolts.
1 March 2006
CROSS Safety Report
Report ID: 19
Region: CROSS-UK
Inadequate underpinning
Works were stopped on site after it was discovered the contractor had completely ignored the specified 5-bay sequence and timing of the underpinning works shown on the design drawings.
1 April 2007
CROSS Safety Report
Report ID: 72
Region: CROSS-UK
Steelwork delivered to site
The contractor on a domestic building project reported that there were deficiencies in steelwork supplied to site.
1 October 2007
CROSS Safety Report
Report ID: 80
Region: CROSS-UK
Design of head track in cold formed steel framing
The reporter noticed that the in-house structural engineer for the steel frame company had not taken account of all the loads in the design of the head track.
1 November 2006
CROSS Safety Report
Report ID: 39
Region: CROSS-UK
Steelwork connection design
A reporter was asked to design connections for a multi-storey building for which the frame had been designed by another engineer. The result was a near collapse situation.
1 March 2006
CROSS Safety Report
Report ID: 25
Region: CROSS-UK
Very slender props
A reporter noticed prop that did not have ties installed while carrying out a site inspection.
1 July 2007
CROSS Safety Report
Report ID: 34
Region: CROSS-UK
Missing starter bars
During an inspection the reporter observed that all the continuity starter bars projecting from the wall kicker were in fact loose.
1 July 2007
CROSS Safety Report
Report ID: 37
Region: CROSS-UK
Submit a report
Your report will make a difference. It will help to create positive change and improve safety.
Our secure and confidential safety reporting system gives professionals the opportunity to share their experiences to help others.